United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Maryland (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8382 MW
Active in queue1,731 MW8 requests
Agreement signed0.0 MW0 requests
Withdrawn8382 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project C01-1013, Charles County
Other Β· Chalk Point Steam, LLC
108 MWWithdrawn / abandoned Charles, MDPJM May 2025
Solar project AG2-615, Allegany County
Solar Β· Squirrel Run Solar, L.L.C.
100 MWWithdrawn / abandoned Allegany, MDPJM Feb 2025target 2023
Battery storage project AG2-281, Queen Anne's County
Battery storage Β· Church Storage LLC
50.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Feb 2025target 2024
Solar + storage project AH1-536, Queen Anne's County
Solar + storage Β· Old Line Energy, LLC
41.8 MWWithdrawn / abandoned Queen Anne's, MDPJM Feb 2025target 2025
Solar project AG2-181, Dorchester County
Solar Β· Old Line Energy, LLC
28.0 MWWithdrawn / abandoned Dorchester, MDPJM Mar 2025target 2024
Solar project AH1-380, Worcester County
Solar Β· Forest Lane Solar, LLC
20.0 MWWithdrawn / abandoned Worcester, MDPJM Feb 2025target 2024
Solar project AG2-279, Washington County
Solar Β· Franklin Energy, LLC
20.0 MWWithdrawn / abandoned Washington, MDPJM Feb 2025target 2024
Hydro project AG2-505, Garrett County
Hydro Β· Fairlawn Hydroelectric Company, LLC
14.0 MWWithdrawn / abandoned Garrett, MDPJM Mar 2025target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)