Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5533 MW
Active in queue533 MW5 requests
Agreement signed0.0 MW0 requests
Withdrawn6352 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Replace 330 MW of CLECO.DPS Unit with solar; Dolet Hills
Other
330 MWIn study De Soto Parish, LAMISO Dec 2020target 2024
Surplus; J909
Other
100 MWIn study Tangipahoa Parish, LAMISO Jan 2025target 2027
Replacing 49 MW of gas generation with BESS; Sterlington
Other
49.0 MWIn study Ouachita, LAMISO Oct 2023target 2025
Other project J868, Concordia Parish County
Other
37.2 MWUnder construction Concordia Parish, LAMISO Jun 2017target 1990
Other project J1247, St. Mary Parish County
Other
17.0 MWUnder construction St. Mary Parish, LAMISO Apr 20192023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)