Withdrawn queue requests in Louisiana (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown182,330 MW
Active in queue2,107 MW12 requests
Agreement signed1,075 MW3 requests
Withdrawn182,330 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1220, Rapides Parish County
Solar
200 MWWithdrawn / abandoned Rapides Parish, LAMISO Apr 2019target 2022
Solar project J1441, Terrebonne Parish County
Solar
200 MWWithdrawn / abandoned Terrebonne Parish, LAMISO Apr 2019target 2025
Solar project J1217, St. Landry Parish County
Solar
200 MWWithdrawn / abandoned St. Landry Parish, LAMISO Apr 2019target 2022
Solar project J1282, Beauregard Parish County
Solar
200 MWWithdrawn / abandoned Beauregard Parish, LAMISO Apr 2019target 2022
Solar project J1380, Beauregard Parish County
Solar
200 MWWithdrawn / abandoned Beauregard Parish, LAMISO Apr 2019target 2023
Solar project J1384, Evangeline Parish County
Solar
200 MWWithdrawn / abandoned Evangeline Parish, LAMISO Apr 2019target 2022
Solar project J1452, Red River Parish County
Solar
200 MWWithdrawn / abandoned Red River Parish, LAMISO Apr 2019target 2022
Solar project J1463, West Baton Rouge Parish, La County
Solar
150 MWWithdrawn / abandoned West Baton Rouge Parish, La, LAMISO Apr 2019target 2023
Solar project J1455, St. Mary Parish County
Solar
150 MWWithdrawn / abandoned St. Mary Parish, LAMISO Apr 2019target 2025
Solar project J1462, Acadia Parish County
Solar
150 MWWithdrawn / abandoned Acadia Parish, LAMISO Apr 2019target 2022
Solar project J1351, Madison Parish County
Solar
120 MWWithdrawn / abandoned Madison Parish, LAMISO Apr 2019target 2022
Solar project J1291, Catahoula Parish County
Solar
100 MWWithdrawn / abandoned Catahoula Parish, LAMISO Apr 2019target 2022
Battery storage project GEN-2019-049, Caddo Parish County
Battery storage
60.0 MWWithdrawn / abandoned Caddo Parish, LASPP May 2019target 2027
Battery storage project J1236, St. Landry Parish County
Battery storage
50.0 MWWithdrawn / abandoned St. Landry Parish, LAMISO Apr 2019target 2022
Battery storage project J1238, Rapides Parish County
Battery storage
50.0 MWWithdrawn / abandoned Rapides Parish, LAMISO Apr 2019target 2022
Solar project J1433, Washington Parish County
Solar
50.0 MWWithdrawn / abandoned Washington Parish, LAMISO Apr 2019target 2021
Battery storage project J1290, Evangeline Parish County
Battery storage
25.0 MWWithdrawn / abandoned Evangeline Parish, LAMISO Apr 2019target 2022
Solar project GEN-2019-080, Natchitoches Parish County
Solar
25.0 MWWithdrawn / abandoned Natchitoches Parish, LASPP Apr 2019target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)