United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Iowa (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown153,703 MW
Active in queue215 MW3 requests
Agreement signed215 MW3 requests
Withdrawn125,020 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J500, Adair County
Onshore wind
500 MWOperating Adair, IAMISO Nov 20152017
Onshore wind project J499, Adair County
Onshore wind
340 MWOperating Adair, IAMISO Nov 20152016
Onshore wind project J498, Boone County
Onshore wind
340 MWOperating Boone, IAMISO Nov 20152017
Onshore wind project J455, Clay County
Onshore wind
300 MWOperating Clay, IAMISO May 20152018
Onshore wind project J534, Humboldt County
Onshore wind
250 MWOperating Humboldt, IAMISO Nov 20152020
Onshore wind project J527, Adair County
Onshore wind
250 MWOperating Adair, IAMISO Nov 20152020
Onshore wind project J529, Palo Alto County
Onshore wind
250 MWOperating Palo Alto, IAMISO Nov 20152018
Onshore wind project J530, Iowa County
Onshore wind
250 MWOperating Iowa, IAMISO Nov 20152020
Onshore wind project J535, Sac County
Onshore wind
210 MWOperating Sac, IAMISO Nov 20152020
Onshore wind project J449, Mitchell County
Onshore wind
202 MWOperating Mitchell, IAMISO May 20152018
Onshore wind project J495, Winnebago County
Onshore wind
200 MWOperating Winnebago, IAMISO Nov 20152019
Onshore wind project J475, Poweshiek County
Onshore wind
200 MWOperating Poweshiek, IAMISO Sep 20152018
Onshore wind project J506, Plymouth County
Onshore wind
200 MWOperating Plymouth, IAMISO Nov 20152019
Onshore wind project J438, Poweshiek County
Onshore wind
170 MWOperating Poweshiek, IAMISO Mar 20152018
Onshore wind project J443, Delaware County
Onshore wind
41.0 MWOperating Delaware, IAMISO May 20152018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)