United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Indiana (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,243 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn101,243 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G935, Clinton County
Onshore wind
201 MWWithdrawn / abandoned Clinton, INMISO Jun 2010target 2010
Onshore wind project G865, Benton County
Onshore wind
201 MWWithdrawn / abandoned Benton, INMISO Nov 2010target 2012
Onshore wind project J156, Marshall County
Onshore wind
186 MWWithdrawn / abandoned Marshall, INMISO Jun 2010
Onshore wind project W3-024, Whitley County
Onshore wind
149 MWWithdrawn / abandoned Whitley, INPJM Aug 2010target 2013
Onshore wind project W3-060, Noble County
Onshore wind
120 MWWithdrawn / abandoned Noble, INPJM Sep 2010target 2012
Onshore wind project W2-044, Whitley County
Onshore wind
101 MWWithdrawn / abandoned Whitley, INPJM Jun 2010target 2011
Onshore wind project J163, Tippecanoe County
Onshore wind
100 MWWithdrawn / abandoned Tippecanoe, INMISO Sep 2010target 2014
Flat Rock - WF-1
Onshore wind
90.0 MWWithdrawn / abandoned Henry, INPJM Nov 2010target 2021
Flat Rock-WF-1
Onshore wind
90.0 MWWithdrawn / abandoned Henry, INPJM Nov 2010target 2021
Other project J152, White County
Other
5.9 MWWithdrawn / abandoned White, INMISO Jun 2010target 2010

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)