United States βΊ Grid βΊ Interconnection queues βΊ Idaho
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Idaho (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Lava Ridge Wind Wind + storage |
1,666 MW | Withdrawn / abandoned |
| Salmon Falls Wind Wind + storage |
1,356 MW | Withdrawn / abandoned |
| Onshore wind project C1-49, Bonneville County Onshore wind |
308 MW | Withdrawn / abandoned |
| Solar + storage project PIS001, Clark County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project PIS003, Clark County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project C1-43, Clark County Solar + storage Β· Jugu Bn, LLC |
200 MW | Withdrawn / abandoned |
| Solar project 623, Bingham County Solar Β· Mosby Butte Solar, LLC |
200 MW | Withdrawn / abandoned |
| Battery storage project 117, Kootenai County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project TCS-17, Kootenai County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project C1-21, Caribou County Solar + storage |
199 MW | Withdrawn / abandoned |
| Solar + storage project 611, Elmore County Solar + storage |
115 MW | Withdrawn / abandoned |
| Solar + storage project 612, Elmore County Solar + storage |
115 MW | Withdrawn / abandoned |
| Solar project 602, Owyhee County Solar |
100 MW | Withdrawn / abandoned |
| Solar project 603, Payette County Solar |
100 MW | Withdrawn / abandoned |
| Solar + storage project 613, Elmore County Solar + storage |
85.0 MW | Withdrawn / abandoned |
| Solar + storage project 617, Clark County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Battery storage project 628, Washington County Battery storage |
4.0 MW | Withdrawn / abandoned |
| Battery storage project 626, Elmore County Battery storage |
4.0 MW | Withdrawn / abandoned |
| Battery storage project 627, Canyon County Battery storage |
2.0 MW | Withdrawn / abandoned |
| Battery storage project 618, Twin Falls County Battery storage |
2.0 MW | Withdrawn / abandoned |
| Hydro project 601, Twin Falls County Hydro |
1.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)