πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Georgia (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3933 MW
Active in queue933 MW3 requests
Agreement signed733 MW2 requests
Withdrawn584,856 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-652, Sumter County
Solar
615 MWAgreement signed Sumter, GASoutheast Sep 2017target 2023
Oakhurst Solar Farm
Solar + storage
200 MWIn study Mitchell, GASoutheast Apr 20172021
Solar project IC-616, Pierce County
Solar
118 MWAgreement signed Pierce, GASoutheast Mar 2017target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)