United States โ€บ Grid โ€บ Interconnection queues โ€บ Georgia

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Georgia (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown512,984 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn512,984 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

51 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-346, Glynn County
Solar
215 MWWithdrawn / abandoned Glynn, GASoutheast Mar 2014
Solar project IC-349, Jeff Davis County
Solar
215 MWWithdrawn / abandoned Jeff Davis, GASoutheast Mar 2014
Solar project IC-374, Putnam County
Solar
151 MWWithdrawn / abandoned Putnam, GASoutheast Apr 2014
Solar project IC-345, Glynn County
Solar
140 MWWithdrawn / abandoned Glynn, GASoutheast Mar 2014
Solar project IC-348, Taylor County
Solar
140 MWWithdrawn / abandoned Taylor, GASoutheast Mar 2014
Solar project IC-375, Putnam County
Solar
121 MWWithdrawn / abandoned Putnam, GASoutheast Apr 2014
Onshore wind project IC-334, Screven County
Onshore wind
112 MWWithdrawn / abandoned Screven, GASoutheast Jan 2014
Solar project IC-368, Sumter County
Solar
100 MWWithdrawn / abandoned Sumter, GASoutheast Apr 2014
Solar project IC-340, Monroe County
Solar
100 MWWithdrawn / abandoned Monroe, GASoutheast Mar 2014
Solar project IC-400, Taylor County
Solar
100 MWWithdrawn / abandoned Taylor, GASoutheast Nov 2014
Solar project IC-352, Oglethorpe County
Solar
100 MWWithdrawn / abandoned Oglethorpe, GASoutheast Apr 2014
Solar project IC-330, Taylor County
Solar
100 MWWithdrawn / abandoned Taylor, GASoutheast Jan 2014
Solar project IC-369, Jenkins County
Solar
87.4 MWWithdrawn / abandoned Jenkins, GASoutheast Apr 2014
Solar project IC-331, Terrell County
Solar
82.0 MWWithdrawn / abandoned Terrell, GASoutheast Jan 2014
Solar project IC-336, Dodge County
Solar
80.0 MWWithdrawn / abandoned Dodge, GASoutheast Feb 2014
Solar project IC-341, Decatur County
Solar
79.9 MWWithdrawn / abandoned Decatur, GASoutheast Mar 2014
Solar project IC-363, Oglethorpe County
Solar
78.0 MWWithdrawn / abandoned Oglethorpe, GASoutheast Apr 2014
Solar project IC-378, Taylor County
Solar
75.0 MWWithdrawn / abandoned Taylor, GASoutheast May 2014
Solar project IC-344, Glynn County
Solar
70.0 MWWithdrawn / abandoned Glynn, GASoutheast Mar 2014
Solar project IC-355, Taylor County
Solar
70.0 MWWithdrawn / abandoned Taylor, GASoutheast Apr 2014
Solar project IC-380, Twiggs County
Solar
60.0 MWWithdrawn / abandoned Twiggs, GASoutheast May 2014
Solar project IC-377, Tattnall County
Solar
50.0 MWWithdrawn / abandoned Tattnall, GASoutheast May 2014
Solar project IC-370, Clinch County
Solar
49.9 MWWithdrawn / abandoned Clinch, GASoutheast Apr 2014
Solar project IC-332, Jenkins County
Solar
43.0 MWWithdrawn / abandoned Jenkins, GASoutheast Jan 2014
Solar project IC-361, Coweta County
Solar
35.6 MWWithdrawn / abandoned Coweta, GASoutheast Apr 2014
Solar project IC-335, Dodge County
Solar
35.0 MWWithdrawn / abandoned Dodge, GASoutheast Feb 2014
Solar project IC-392, Taylor County
Solar
30.0 MWWithdrawn / abandoned Taylor, GASoutheast Aug 2014
Solar project IC-362, Putnam County
Solar
29.7 MWWithdrawn / abandoned Putnam, GASoutheast Apr 2014
Solar project IC-384, Richmond County
Solar
29.3 MWWithdrawn / abandoned Richmond, GASoutheast Jun 2014
Solar project IC-360, Colquitt County
Solar
20.0 MWWithdrawn / abandoned Colquitt, GASoutheast Apr 2014
Solar project IC-353, Clay County
Solar
20.0 MWWithdrawn / abandoned Clay, GASoutheast Apr 2014
Solar project IC-357, Colquitt County
Solar
20.0 MWWithdrawn / abandoned Colquitt, GASoutheast Apr 2014
Solar project IC-376, Brooks County
Solar
20.0 MWWithdrawn / abandoned Brooks, GASoutheast Apr 2014
Solar project IC-359, Ben Hill County
Solar
20.0 MWWithdrawn / abandoned Ben Hill, GASoutheast Apr 2014
Solar project IC-358, Mitchell County
Solar
20.0 MWWithdrawn / abandoned Mitchell, GASoutheast Apr 2014
Solar project IC-366, Lowndes County
Solar
20.0 MWWithdrawn / abandoned Lowndes, GASoutheast Apr 2014
Solar project IC-350, Montgomery County
Solar
20.0 MWWithdrawn / abandoned Montgomery, GASoutheast Apr 2014
Solar project IC-383, Mitchell County
Solar
20.0 MWWithdrawn / abandoned Mitchell, GASoutheast Jun 2014
Solar project IC-351, Bacon County
Solar
19.8 MWWithdrawn / abandoned Bacon, GASoutheast Apr 2014
Solar project IC-372, Mitchell County
Solar
19.6 MWWithdrawn / abandoned Mitchell, GASoutheast Apr 2014
Solar project IC-371, Mitchell County
Solar
19.6 MWWithdrawn / abandoned Mitchell, GASoutheast Apr 2014
Solar project IC-373, Putnam County
Solar
19.6 MWWithdrawn / abandoned Putnam, GASoutheast Apr 2014
Solar project IC-354, Peach County
Solar
19.4 MWWithdrawn / abandoned Peach, GASoutheast Apr 2014
Solar project IC-367, Bacon County
Solar
18.5 MWWithdrawn / abandoned Bacon, GASoutheast Apr 2014
Solar project IC-337, Calhoun County
Solar
18.5 MWWithdrawn / abandoned Calhoun, GASoutheast Feb 2014
Solar project IC-338, Dodge County
Solar
18.5 MWWithdrawn / abandoned Dodge, GASoutheast Feb 2014
Solar project IC-389, Baldwin County
Solar
18.4 MWWithdrawn / abandoned Baldwin, GASoutheast Jul 2014
Solar project IC-365, Candler County
Solar
17.3 MWWithdrawn / abandoned Candler, GASoutheast Apr 2014
Solar project IC-382, Camden County
Solar
16.0 MWWithdrawn / abandoned Camden, GASoutheast Jun 2014
Solar project IC-342, Houston County
Solar
9.8 MWWithdrawn / abandoned Houston, GASoutheast Mar 2014
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)