ONSHORE WIND Β· SOUTHEAST

Onshore wind project IC-334, Screven County

Onshore wind project IC-334, Screven County is a 112 MW onshore wind request withdrawn in the Southeast interconnection queue, in Screven County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2014 (completed)
  2. Withdrawn / abandonedDec 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-334
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Millen Primary - Sylvania 115 kV Line
Location
Screven County, Georgia
Technology
Wind: 112 MW
Total requested
112 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
31 January 2014
Withdrawn
December 2014

Location

Marker shows the centre of Screven County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Screven County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem