United States βΊ Grid βΊ Interconnection queues βΊ Georgia
ONSHORE WIND Β· SOUTHEASTOnshore wind project IC-334, Screven County
Onshore wind project IC-334, Screven County is a 112 MW onshore wind request withdrawn in the Southeast interconnection queue, in Screven County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2014 (completed)
- Withdrawn / abandonedDec 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-334
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Millen Primary - Sylvania 115 kV Line
- Location
- Screven County, Georgia
- Technology
- Wind: 112 MW
- Total requested
- 112 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 31 January 2014
- Withdrawn
- December 2014
Location
Marker shows the centre of Screven County; the queue data does not give exact sites.
Other requests in Screven County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem