πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

SOLAR Β· SOUTHEAST

Solar project IC-348, Taylor County

Solar project IC-348, Taylor County is a 140 MW solar request withdrawn in the Southeast interconnection queue, in Taylor County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2014 (completed)
  2. Withdrawn / abandonedFeb 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-348
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Butler Substation 230 kV Bus
Location
Taylor County, Georgia
Technology
Solar: 140 MW
Total requested
140 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
21 March 2014
Withdrawn
February 2015

Location

Marker shows the centre of Taylor County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Taylor County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem