United States βΊ Grid βΊ Interconnection queues βΊ Georgia
SOLAR Β· SOUTHEASTSolar project IC-354, Peach County
Solar project IC-354, Peach County is a 19.4 MW solar request withdrawn in the Southeast interconnection queue, in Peach County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2014 (completed)
- Withdrawn / abandonedNov 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-354
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Fort Valley - Beaver Creek 46 kV Line
- Location
- Peach County, Georgia
- Technology
- Solar: 19.4 MW
- Total requested
- 19.4 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 17 April 2014
- Withdrawn
- November 2015
Location
Marker shows the centre of Peach County; the queue data does not give exact sites.
Other requests in Peach County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem