United States › Grid › Interconnection queues › Florida

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Florida (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown544,026 MW
Active in queue4,026 MW54 requests
Agreement signed75.0 MW1 requests
Withdrawn473,356 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

54 requests · page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 425A, Jackson County
Solar + storage · Third Party
75.0 MWAgreement signed Jackson, FLSoutheast Feb 2022target 2029
Solar project 307, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 319, Hernando County
Solar · Duke Energy Florida, LLC
74.9 MWPaused / redesign Hernando, FLSoutheast Dec 2022target 2026
Solar project 322, Sumter County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Sumter, FLSoutheast Dec 2022target 2026
Solar project 320, Hernando County
Solar · Duke Energy Florida, LLC
74.9 MWPaused / redesign Hernando, FLSoutheast Dec 2022target 2027
Solar project 305, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 308, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 473, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2029
Solar project 454, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2030
Solar project 453, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2031
Solar project 437, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Mar 2022target 2026
Solar project 438, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Mar 2022target 2028
Solar project 475, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2032
Solar project 451, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 465, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2029
Solar project 461, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2028
Solar project 434, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2027
Solar project 457, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 430, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2026
Solar project 455, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2031
Solar project 471, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2029
Solar project 460, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2026
Solar project 462, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2029
Solar project 448, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 444, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2026
Solar project 459, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2026
Solar project 449, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 446, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2028
Solar project 456, Indian River County
Solar · FPL
74.5 MWIn study Indian River, FLSoutheast Apr 2022target 2031
Solar project 314, Levy County
Solar · Florida Renewable Partners, LLC
74.5 MWPaused / redesign Levy, FLSoutheast Aug 2022target 2026
Solar project 429, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2027
Solar project 489, Calhoun County
Solar · FPL
74.5 MWIn study Calhoun, FLSoutheast Aug 2022target 2026
Solar project 425B, Gadsden County
Solar · FPL
74.5 MWIn study Gadsden, FLSoutheast Feb 2022target 2033
Solar project 431, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Mar 2022target 2026
Solar project 458, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 432, Indian River County
Solar · FPL
74.5 MWIn study Indian River, FLSoutheast Mar 2022target 2027
Solar project 476, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2032
Solar project 478, Highlands County
Solar · FPL
74.5 MWIn study Highlands, FLSoutheast Jul 2022target 2029
Solar project 477, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2030
Solar project 472, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2029
Solar project 315, Levy County
Solar · Florida Renewable Partners, LLC
74.5 MWPaused / redesign Levy, FLSoutheast Aug 2022target 2026
Solar project 439, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2028
Solar project 452, Indian River County
Solar · FPL
74.5 MWIn study Indian River, FLSoutheast Apr 2022target 2029
Solar project 447, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2027
Solar project 450, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2030
Solar project 433, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Mar 2022target 2028
Solar project 464, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2028
Solar project 463, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2028
Solar project 445, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2028
Solar project 312, Alachua County
Solar · Florida Renewable Partners, LLC
74.5 MWPaused / redesign Alachua, FLSoutheast Apr 2022target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)