United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Florida (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown94,935 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn94,935 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 110, Pasco County
Gas Β· Duke Energy Florida, LLC
1,400 MWWithdrawn / abandoned Pasco, FLSoutheast Jul 2011target 2018
Gas project 109, Pasco County
Gas Β· Duke Energy Florida, LLC
1,400 MWWithdrawn / abandoned Pasco, FLSoutheast Jul 2011target 2016
Gas project 111, Citrus County
Gas Β· Duke Energy Florida, LLC
950 MWWithdrawn / abandoned Citrus, FLSoutheast Jul 2011target 2018
Gas project 112, Suwannee County
Gas Β· Masked
950 MWWithdrawn / abandoned Suwannee, FLSoutheast Jul 2011target 2018
Solar project 113, Lake County
Solar Β· Masked
100 MWWithdrawn / abandoned Lake, FLSoutheast Aug 2011target 2011
Other project 108, Gulf County
Other Β· Masked
61.5 MWWithdrawn / abandoned Gulf, FLSoutheast Mar 2011target 2013
Other project 107, Orange County
Other Β· Masked
36.0 MWWithdrawn / abandoned Orange, FLSoutheast Feb 2011
Solar project 115, Hardee County
Solar Β· Masked
20.0 MWWithdrawn / abandoned Hardee, FLSoutheast Oct 2011target 2013
Other project 114, Taylor County
Other Β· Masked
17.0 MWWithdrawn / abandoned Taylor, FLSoutheast Sep 2011

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)