Interconnection queue in Colorado (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown204,095 MW
Active in queue4,095 MW20 requests
Agreement signed1,575 MW7 requests
Withdrawn244,267 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

20 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GI-DISIS-2022-13, Prowers County
Solar + storage
398 MWAgreement signed Prowers, COWest May 2022target 2029
Solar + storage project GI-DISIS-2022-28, Kit Carson County
Solar + storage
299 MWPaused / redesign Kit Carson, COWest May 2022target 2029
Solar + storage project GI-DISIS-2022-45, Pueblo County
Solar + storage
299 MWPaused / redesign Pueblo, COWest May 2022target 2028
Solar + storage project GI-DISIS-2022-44, Moffat County
Solar + storage
299 MWPaused / redesign Moffat, COWest May 2022target 2030
Solar + storage project GI-DISIS-2022-02, Weld County
Solar + storage
299 MWAgreement signed Weld, COWest May 2022target 2030
Solar + storage project GI-DISIS-2022-07, Weld County
Solar + storage
299 MWAgreement signed Weld, COWest May 2022target 2029
Gas project 22-07251, Larimer County
Gas
250 MWIn study Larimer, COWest Jul 2022target 2028
Solar + storage project GI-DISIS-2022-04, Kit Carson County
Solar + storage
237 MWAgreement signed Kit Carson, COWest May 2022target 2027
Solar + storage project GI-DISIS-2022-49, Prowers County
Solar + storage
225 MWPaused / redesign Prowers, COWest May 2022target 2029
Wind + storage project 22-07252, Larimer County
Wind + storage
200 MWIn study Larimer, COWest Jul 2022target 2026
Battery storage project GI-2011-2 & 7, Arapahoe County
Battery storage
200 MWPaused / redesign Arapahoe, COWest Sep 2022target 2025
Onshore wind project GI-DISIS-2022-29, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest May 2022target 2029
Solar + storage project BHCT G33, Pueblo County
Solar + storage
199 MWIn study Pueblo, COWest Jun 2022target 2025
Onshore wind project GI-DISIS-2022-17, Kiowa County
Onshore wind
199 MWPaused / redesign Kiowa, COWest May 2022target 2030
Solar + storage project BHCT G35, Pueblo County
Solar + storage
150 MWIn study Pueblo, COWest Aug 2022target 2026
Solar + storage project BHCT G32, Pueblo County
Solar + storage
100 MWIn study Pueblo, COWest Apr 2022target 2025
Solar + storage project GI-DISIS-2022-22, Kit Carson County
Solar + storage
90.0 MWAgreement signed Kit Carson, COWest May 2022target 2028
Gas project GI-2022-1, Weld County
Gas
52.0 MWAgreement signed Weld, COWest Mar 2022target 2023
Battery storage project 22-07253, Weld County
Battery storage
50.0 MWIn study Weld, COWest Jul 2022target 2026
Onshore wind project GI-DISIS-2022-41, Kit Carson County
Onshore wind
49.6 MWPaused / redesign Kit Carson, COWest May 2022target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)