United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Colorado (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4340 MW
Active in queue340 MW4 requests
Agreement signed260 MW3 requests
Withdrawn5813.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2017-12, Weld County
Onshore wind
170 MWAgreement signed Weld, COWest Apr 20172020
Solar project BHCT G21, Pueblo County
Solar
80.0 MWIn study Pueblo, COWest Jan 2017target 2018
Solar project GI-2017-5, Park County
Solar
54.3 MWAgreement signed Park, COWest Jan 2017target 2019
Solar project GI-2017-52, El Paso County
Solar
36.0 MWAgreement signed El Paso, COWest Dec 20172019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)