United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OCTARY USA Β· INTERCONNECTION QUEUES

Onshore wind interconnection queue in California

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown122,267 MW
Active in queue2,267 MW12 requests
Agreement signed1,144 MW9 requests
Withdrawn15246.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project Company MY, Lassen County
Onshore wind
715 MWPaused / redesign Lassen, CAWest Mar 2022target 2032
Mount Laguna Wind 2
Onshore wind
400 MWAgreement signed San Diego, CACAISO May 2017target 2031
Onshore wind project Company LF, Lassen County
Onshore wind
300 MWPaused / redesign Lassen, CAWest Mar 2021target 2023
Fountain Wind
Onshore wind
206 MWAgreement signed Shasta, CACAISO Apr 2015target 2027
Mulqueeney Ranch Wind
Onshore wind
114 MWAgreement signed Alameda, CACAISO May 2016target 2026
Toland Renewable Energy Park
Onshore wind
108 MWIn study Solano, CACAISO Apr 2023target 2029
Keyhole Wind
Onshore wind
100 MWAgreement signed Kern, CACAISO Apr 2020target 2028
Solano 4 Wind
Onshore wind
92.4 MWAgreement signed Solano, CACAISO Apr 2018target 2025
Sand Hill C
Onshore wind
84.3 MWAgreement signed Alameda, CACAISO May 2017target 2027
Gonzaga Wind Farm
Onshore wind
80.0 MWAgreement signed Merced, CACAISO May 2017target 2026
Mulqueeney Ranch Wind 2
Onshore wind
62.5 MWAgreement signed Alameda, CACAISO Apr 2018target 2026
Altamont Midway LTD
Onshore wind
5.0 MWAgreement signed Alameda, CACAISO Apr 2015target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)