United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in California (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown112,277 MW
Active in queue6,711 MW22 requests
Agreement signed250 MW1 requests
Withdrawn112,277 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 2022-G1, Sutter County
Solar + storage
300 MWWithdrawn / abandoned Sutter, CAWest Oct 2022target 2025
Ventana Energy Storage
Battery storage
254 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2022target 2024
Battery storage project 28, Sacramento County
Battery storage
250 MWWithdrawn / abandoned Sacramento, CAWest Nov 2022target 2028
Battery storage project 24, Sacramento County
Battery storage
250 MWWithdrawn / abandoned Sacramento, CAWest Aug 2022target 2028
Battery storage project 23, Sacramento County
Battery storage
250 MWWithdrawn / abandoned Sacramento, CAWest Aug 2022target 2027
Battery storage project 21, Sacramento County
Battery storage
230 MWWithdrawn / abandoned Sacramento, CAWest Jul 2022target 2027
Battery storage project 17, Sacramento County
Battery storage
200 MWWithdrawn / abandoned Sacramento, CAWest Jan 2022target 2025
Battery storage project 18, Sacramento County
Battery storage
200 MWWithdrawn / abandoned Sacramento, CAWest Mar 2022target 2024
Pronghorn Energy Storage
Battery storage
123 MWWithdrawn / abandoned Los Angeles, CACAISO Jun 2022target 2026
Battery storage project 19, Sacramento County
Battery storage
120 MWWithdrawn / abandoned Sacramento, CAWest May 2022target 2025
Battery storage project 29, Sacramento County
Battery storage
100 MWWithdrawn / abandoned Sacramento, CAWest Dec 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)