United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Arkansas (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6850 MW
Active in queue850 MW6 requests
Agreement signed0.0 MW0 requests
Withdrawn174,765 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2022-130, Sebastian County
Battery storage
200 MWIn study Sebastian, ARSPP Feb 2023target 2030
Solar project J2759, Arkansas County
Solar
170 MWIn study Arkansas, ARMISO Sep 2023target 2029
Solar project J2955, Saline County
Solar
150 MWIn study Saline, ARMISO Nov 2023target 2026
Solar project GEN-2023-132, Craighead County
Solar
150 MWIn study Craighead, ARSPP Oct 2023target 2028
Solar project J2801, Woodruff County
Solar
130 MWIn study Woodruff, ARMISO Sep 2023target 2026
Battery storage project GEN-2023-206, Sebastian County
Battery storage
50.0 MWIn study Sebastian, ARSPP Oct 2023target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)