Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown102,621 MW
Active in queue2,621 MW10 requests
Agreement signed245 MW3 requests
Withdrawn28939.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q274, Coconino County
Solar
1,000 MWIn study Coconino, AZWest Mar 2018target 2024
Domestic Chicken
Solar
559 MWIn study Maricopa, AZCAISO Apr 2023target 2029
Solar project Q312, Coconino County
Solar
500 MWIn study Coconino, AZWest Sep 2019target 2021
Solar project Q230, Navajo County
Solar
200 MWUnder construction Navajo, AZWest Sep 2015target 2021
Saddle Mountain Solar
Solar
125 MWAgreement signed Maricopa, AZCAISO Apr 2020target 2025
Solar project Q254, Pinal County
Solar
100 MWAgreement signed Pinal, AZWest Mar 2017target 2022
Solar project Q104, Pinal County
Solar
51.3 MWIn study Pinal, AZWest May 2023target 2025
Solar project Q346, Maricopa County
Solar
45.0 MWPaused / redesign Maricopa, AZWest Apr 2020target 2021
Solar project Q246, Yuma County
Solar
20.0 MWAgreement signed Yuma, AZWest Sep 2016target 2021
Agua Caliente Solar 2
Solar
20.0 MWIn study Maricopa, AZCAISO Mar 2016target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)