United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Arizona (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown364,766 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn364,766 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

36 requests
ProjectCapacityStatusLocationRegionQueuedOnline
CVH Power II
Solar
700 MWWithdrawn / abandoned Maricopa, AZCAISO Mar 2011target 2014
Solar project Q17, Maricopa County
Solar
700 MWWithdrawn / abandoned Maricopa, AZWest Apr 2011target 2014
Solar project Q193, Maricopa County
Solar
450 MWWithdrawn / abandoned Maricopa, AZWest Mar 2011target 2015
Other project Q197, Coconino County
Other
302 MWWithdrawn / abandoned Coconino, AZWest May 2011target 2013
Solar project Q184, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Jan 2011target 2017
Solar project Q16, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Apr 2011target 2014
CVH Power I
Solar
300 MWWithdrawn / abandoned Maricopa, AZCAISO Mar 2011target 2014
Onshore wind project Q203, Coconino County
Onshore wind
250 MWWithdrawn / abandoned Coconino, AZWest Jul 2011target 2014
Arlington Valley Solar Energy II
Solar
250 MWWithdrawn / abandoned Maricopa, AZCAISO Mar 2011target 2015
Hyder Solar Energy Project
Solar
250 MWWithdrawn / abandoned Yuma, AZCAISO Mar 2011target 2014
Sun Valley Energy Center-1
Solar
200 MWWithdrawn / abandoned Maricopa, AZCAISO Nov 2011target 2016
Areva Solar Az I
Solar
150 MWWithdrawn / abandoned Yuma, AZCAISO Mar 2011target 2015
Solar project Q201, Maricopa County
Solar
150 MWWithdrawn / abandoned Maricopa, AZWest Jun 2011target 2014
Solar project Q209, Yuma County
Solar
50.0 MWWithdrawn / abandoned Yuma, AZWest Oct 2011target 2014
Solar project Q208, Yuma County
Solar
50.0 MWWithdrawn / abandoned Yuma, AZWest Oct 2011target 2013
Solar project Q207, Pinal County
Solar
30.0 MWWithdrawn / abandoned Pinal, AZWest Oct 2011target 2013
Solar project Q187, Maricopa County
Solar
25.0 MWWithdrawn / abandoned Maricopa, AZWest Feb 2011target 2012
Solar project Q177, Maricopa County
Solar
25.0 MWWithdrawn / abandoned Maricopa, AZWest Jan 2011target 2013
Solar project Q200, Yavapai County
Solar
20.0 MWWithdrawn / abandoned Yavapai, AZWest Jun 2011target 2014
Solar project Q190, Cochise County
Solar
20.0 MWWithdrawn / abandoned Cochise, AZWest Mar 2011target 2012
Solar project Q192, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2011target 2018
Solar project Q199, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Jun 2011target 2013
Solar project Q176, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Jan 2011target 2012
Solar project Q25, Pinal County
Solar
19.0 MWWithdrawn / abandoned Pinal, AZWest Oct 2011target 2012
Solar project Q204, Yuma County
Solar
19.0 MWWithdrawn / abandoned Yuma, AZWest Sep 2011target 2013
Solar project Q195, Maricopa County
Solar
16.0 MWWithdrawn / abandoned Maricopa, AZWest Apr 2011target 2013
Solar project Q194, Yavapai County
Solar
16.0 MWWithdrawn / abandoned Yavapai, AZWest Apr 2011target 2013
Solar project Q211, Yuma County
Solar
16.0 MWWithdrawn / abandoned Yuma, AZWest Nov 2011target 2013
Solar project Q186, Yuma County
Solar
16.0 MWWithdrawn / abandoned Yuma, AZWest Feb 2011target 2016
Solar project Q191, Pinal County
Solar
15.0 MWWithdrawn / abandoned Pinal, AZWest Mar 2011target 2013
Solar project Q185, Cochise County
Solar
15.0 MWWithdrawn / abandoned Cochise, AZWest Jan 2011target 2012
Solar project Q210, Yavapai County
Solar
15.0 MWWithdrawn / abandoned Yavapai, AZWest Oct 2011target 2014
Solar project Q206, Yuma County
Solar
12.0 MWWithdrawn / abandoned Yuma, AZWest Oct 2011
Solar project Q189, Maricopa County
Solar
12.0 MWWithdrawn / abandoned Maricopa, AZWest Feb 2011target 2013
Solar project Q188, Maricopa County
Solar
8.0 MWWithdrawn / abandoned Maricopa, AZWest Feb 2011target 2012
Solar project Q175, Maricopa County
Solar
5.0 MWWithdrawn / abandoned Maricopa, AZWest Jan 2011target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)