OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Arizona (2010 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Wildcat Quartszite Solar |
1,000 MW | Withdrawn / abandoned |
| Other project Q173, Maricopa County Other |
620 MW | Withdrawn / abandoned |
| Other project Q169, Maricopa County Other |
600 MW | Withdrawn / abandoned |
| Fort Mojave Solar Solar |
310 MW | Withdrawn / abandoned |
| Palmas (Fka Hyder Solar) Solar |
238 MW | Withdrawn / abandoned |
| Solar project Q13, Maricopa County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project Q106, Navajo County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project Q09, Navajo County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project Q08, Navajo County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project Q107, Yavapai County Onshore wind |
120 MW | Withdrawn / abandoned |
| Onshore wind project Q96, Navajo County Onshore wind |
108 MW | Withdrawn / abandoned |
| Onshore wind project Q142, Apache County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Solar project Q97, Maricopa County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q143, Maricopa County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q10, Pinal County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q165, Maricopa County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q98, Maricopa County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q114, La Paz County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q145, Maricopa County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q137, Navajo County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q13, Pinal County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project Q112, Maricopa County Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project Q110, Maricopa County Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project Q111, Maricopa County Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project Q109, Maricopa County Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project Q127, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q104, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q22, Pinal County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q101, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q168, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q152, Yuma County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q160, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q121, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q128, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q156, Navajo County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q148, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q147, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q116, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q163, Yuma County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q16, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q140, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q99, La Paz County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q135, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q12, Pinal County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q19, Pinal County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q167, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q174, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q103, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q11, Pinal County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q146, La Paz County Solar |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)