United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Arizona (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown91,571 MW
Active in queue6,694 MW18 requests
Agreement signed2,067 MW3 requests
Withdrawn288,688 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q25, Maricopa County
Solar + storage
306 MWOperating Maricopa, AZWest Feb 2018target 2024
Battery storage project Q50, Maricopa County
Battery storage
250 MWOperating Maricopa, AZWest Oct 2018target 2025
Battery storage project Q01, Maricopa County
Battery storage
250 MWOperating Maricopa, AZWest Sep 2018target 2024
Solar project Q47, Pinal County
Solar
200 MWOperating Pinal, AZWest Sep 2018target 2023
Battery storage project Q292, Maricopa County
Battery storage
200 MWOperating Maricopa, AZWest Sep 2018target 2021
Solar project Q276, Maricopa County
Solar
150 MWOperating Maricopa, AZWest Mar 2018target 2022
Battery storage project Q44, Pinal County
Battery storage
100 MWOperating Pinal, AZWest Apr 2018target 2023
Battery storage project Q49, Maricopa County
Battery storage
90.0 MWOperating Maricopa, AZWest Sep 2018target 2024
Battery storage project Q46, Maricopa County
Battery storage
25.0 MWOperating Maricopa, AZWest Aug 20182021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)