🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arizona

BATTERY STORAGE · WEST

Battery storage project Q292, Maricopa County

Battery storage project Q292, Maricopa County is a 200 MW battery storage request built and operating in the West interconnection queue, in Maricopa County, Arizona, connecting to Arizona Public Service.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q292
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Westwing 230kV Substation
Location
Maricopa County, Arizona
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
In-Service
Queue status
Operational
Entered queue
29 September 2018
Proposed online date
December 2021

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Maricopa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem