BATTERY STORAGE · WEST

Battery storage project Q50, Maricopa County

Battery storage project Q50, Maricopa County is a 250 MW battery storage request built and operating in the West interconnection queue, in Maricopa County, Arizona, connecting to Salt River Project.

Queue statusOperating
  1. PlanningQueued Oct 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q50
Grid region
West (non-ISO utilities)
Utility / transmission owner
Salt River Project
Connection point (POI)
Browning 230 kV
Location
Maricopa County, Arizona
Technology
Battery: 250 MW
Total requested
250 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
5 October 2018
Proposed online date
November 2025

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Maricopa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem