United States βΊ Grid βΊ Interconnection queues βΊ Alabama
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Alabama (2024 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project IC-1266, Bullock County Solar |
200 MW | Agreement signed |
| Solar project IC-1225, Baldwin County Solar |
180 MW | Agreement signed |
| Solar + storage project IC-1234, Marengo County Solar + storage |
175 MW | Paused / redesign |
| Solar project IC-1251, Lee County Solar |
157 MW | Paused / redesign |
| Solar project 662, Madison County Solar |
110 MW | In study |
| Solar project 660, Jackson County Solar |
99.0 MW | In study |
| Solar project IC-1224, Baldwin County Solar |
80.0 MW | Agreement signed |
| Nuclear project 625, Limestone County Nuclear |
6.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)