πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Alabama (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,007 MW
Active in queue1,007 MW8 requests
Agreement signed460 MW3 requests
Withdrawn112,004 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-1266, Bullock County
Solar
200 MWAgreement signed Bullock, ALSoutheast Mar 2024target 2027
Solar project IC-1225, Baldwin County
Solar
180 MWAgreement signed Baldwin, ALSoutheast Jan 2024target 2028
Solar + storage project IC-1234, Marengo County
Solar + storage
175 MWPaused / redesign Marengo, ALSoutheast Jan 2024target 2028
Solar project IC-1251, Lee County
Solar
157 MWPaused / redesign Lee, ALSoutheast Mar 2024target 2028
Solar project 662, Madison County
Solar
110 MWIn study Madison, ALSoutheast Oct 2024target 2027
Solar project 660, Jackson County
Solar
99.0 MWIn study Jackson, ALSoutheast Oct 2024target 2032
Solar project IC-1224, Baldwin County
Solar
80.0 MWAgreement signed Baldwin, ALSoutheast Jan 2024target 2028
Nuclear project 625, Limestone County
Nuclear
6.0 MWIn study Limestone, ALSoutheast Jun 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)