United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown162,568 MW
Active in queue2,568 MW16 requests
Agreement signed856 MW11 requests
Withdrawn1519,551 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project G0501, Klamath County
Gas
1,100 MWIn study Klamath, ORWest Oct 2014target 2018
Onshore wind project GI-1404, Billings County
Onshore wind
383 MWIn study Billings, NDWest May 2014
Solar + storage project Q225, Maricopa County
Solar + storage
200 MWIn study Maricopa, AZWest Sep 2014target 2021
Solar project GI-2014-9, Pueblo County
Solar
120 MWAgreement signed Pueblo, COWest Oct 2014target 2016
Onshore wind project GI-1401, Butte County
Onshore wind
103 MWAgreement signed Butte, SDWest Jan 2014
Solar project Company 140, Clark County
Solar
100 MWAgreement signed Clark, NVWest Sep 2014target 2025
Solar project 634, Beaver County
Solar Β· Fremont Solar, LLC
99.0 MWAgreement signed Beaver, UTWest Nov 2014target 2025
Solar project 636, Iron County
Solar Β· Rush Lake Solar, LLC
99.0 MWAgreement signed Iron, UTWest Dec 2014target 2025
Gas project IA-PNM-2014-02, San Juan County
Gas
80.0 MWAgreement signed San Juan, NMWest Feb 2014target 2018
Onshore wind project GI-2014-4, Logan County
Onshore wind
60.0 MWAgreement signed Logan, COWest Apr 2014target 2013
Solar project GI-2014-13, Alamosa County
Solar
53.0 MWAgreement signed Alamosa, COWest Nov 2014target 2016
Solar project GI-2014-14, Alamosa County
Solar
50.1 MWAgreement signed Alamosa, COWest Dec 2014target 2016
Solar project GI-2014-5, Arapahoe County
Solar
50.0 MWAgreement signed Arapahoe, COWest May 2014target 2016
Hydro project GI-2014-7, Clear Creek County
Hydro
42.0 MWAgreement signed Clear Creek, COWest Jul 2014target 2019
Geothermal project IA-PNM-2014-04, Dona Ana Cty County
Geothermal
29.0 MWIn study Dona Ana Cty, NMWest Mar 2014target 2018
Gas project 41, Lincoln County
Gas
0.3 MWIn study Lincoln, WAWest Apr 2014target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)