United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESQueue projects under construction in West (non-ISO utilities)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project Q269, Maricopa County Battery storage |
450 MW | Under construction |
| Wind + storage project TCS-14, Garfield County Wind + storage |
375 MW | Under construction |
| Solar + storage project Q332, Maricopa County Solar + storage |
350 MW | Under construction |
| Solar + storage project Q350, Yuma County Solar + storage |
300 MW | Under construction |
| Solar + storage project Q252, Yuma County Solar + storage |
250 MW | Under construction |
| Solar project Q03, Kern County Solar |
250 MW | Under construction |
| Solar + storage project Q270, Navajo County Solar + storage |
200 MW | Under construction |
| Solar project Q230, Navajo County Solar |
200 MW | Under construction |
| Battery storage project Q357, Maricopa County Battery storage |
150 MW | Under construction |
| Solar project 18-11071, Larimer County Solar |
150 MW | Under construction |
| Battery storage project Q268, Maricopa County Battery storage |
75.0 MW | Under construction |
| Battery storage project Q271, Navajo County Battery storage |
75.0 MW | Under construction |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)122 Β· 19.8 GW
- Southeast (non-ISO utilities)60 Β· 5,029 MW
- West (non-ISO utilities)12 Β· 2,825 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)