United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown11977 MW
Active in queue977 MW11 requests
Agreement signed753 MW8 requests
Withdrawn21225.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-53, Nodaway County
Onshore wind
238 MWAgreement signed Nodaway, MOSoutheast May 2016target 2018
Solar project IC-441, Decatur County
Solar
189 MWAgreement signed Decatur, GASoutheast Feb 2016target 2028
Solar project 305, Fayette County
Solar
147 MWAgreement signed Fayette, TNSoutheast Nov 2016target 2026
Solar project 292, Lake County
Solar
80.0 MWAgreement signed Lake, TNSoutheast Apr 2016target 2023
Solar project 171, Gilchrist County
Solar Β· Florida Renewable Partners, LLC
74.5 MWIn study Gilchrist, FLSoutheast Dec 2016target 2021
Solar project 191, Manatee County
Solar Β· FPL
74.5 MWIn study Manatee, FLSoutheast May 2016target 2026
Solar project 151, Columbia County
Solar Β· Duke Energy Florida, LLC
74.5 MWIn study Columbia, FLSoutheast Jul 2016target 2019
Solar project 299, Lake County
Solar
67.0 MWAgreement signed Lake, TNSoutheast Jul 2016target 2020
Gas project 304, Shelby County
Gas
14.0 MWAgreement signed Shelby, TNSoutheast Nov 2016target 2018
Solar project 24747, Buncombe County
Solar Β· Duke Energy Progress, LLC
9.5 MWAgreement signed Buncombe, NCSoutheast Dec 2016target 2026
Solar project LGE-GIS-2016-001, Clark County
Solar
9.0 MWAgreement signed Clark, KYSoutheast Mar 2016target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)