United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in PJM (Mid-Atlantic, Midwest) (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown72,928 MW
Active in queue2,928 MW7 requests
Agreement signed2,680 MW6 requests
Withdrawn23127.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Trumbull Energy Center
Gas
940 MWAgreement signed Trumbull, OHPJM Oct 2015target 2026
Sullivan Generating Station 1
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Sullivan Generating Station 2
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Glen Falls Facility
Gas
550 MWAgreement signed Harrison, WVPJM Apr 2015target 2029
Maryland Offshore Wind Energy Project (MOWEP)
Offshore wind
248 MWPaused / redesign Sussex, DEPJM Aug 2015target 2027
Mountaineer #1
Coal
36.0 MWAgreement signed WVPJM Oct 20152018
Cedar Lane Solar
Solar
4.0 MWAgreement signed Queen Anne's, MDPJM Oct 2015target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)