United States β€Ί Grid β€Ί Interconnection queues β€Ί North Carolina

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in North Carolina, PJM

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown131,308 MW
Active in queue1,846 MW22 requests
Agreement signed1,308 MW13 requests
Withdrawn13711.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Macadamia Solar
Solar
300 MWAgreement signed Washington, NCPJM Sep 2017target 2028
Cherry Solar
Solar
180 MWAgreement signed Northampton, NCPJM Oct 2016target 2025
Shawboro Solar
Solar
150 MWAgreement signed Currituck, NCPJM Jul 2018target 2027
Macadamia Solar
Solar
109 MWAgreement signed Washington, NCPJM Aug 2017target 2028
Swift Creek Solar
Solar + storage
100 MWAgreement signed Edgecombe, NCPJM Mar 2020target 2029
Halifax County Solar
Solar
80.0 MWAgreement signed Halifax, NCPJM Nov 2016target 2026
Currituck Solar
Solar Β· Currituck Solar, LLC
80.0 MWAgreement signed Currituck, NCPJM Jan 2020target 2031
Pitt Solar
Solar
80.0 MWAgreement signed Pitt, NCPJM Oct 2016target 2026
Sumac Solar
Solar
80.0 MWAgreement signed Bertie, NCPJM Jun 2017target 2028
Macadamia Solar
Solar
75.0 MWAgreement signed Washington, NCPJM Aug 2017target 2028
Albemarle Beach Solar
Solar
60.0 MWAgreement signed Washington, NCPJM Jan 2019target 2026
Lillie Solar
Solar
9.4 MWAgreement signed Edgecombe, NCPJM May 2020target 2028
NC3 Ahoskie South Solar Project
Solar + storage
5.0 MWAgreement signed Hertford, NCPJM Jun 2020target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)