United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Kentucky, PJM (2025 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project AH1-721 Gas Β· East Kentucky Power Cooperative, Inc. |
786 MW | In study |
| Solar project AG2-184, Knott County Solar Β· STMO bn, LLC |
210 MW | In study |
| Solar project AH1-617 Solar Β· STMO bn, LLC |
200 MW | In study |
| Solar project AH1-664, Fleming County Solar Β· Hummingbird Energy LLC |
100 MW | In study |
| Solar project AH1-239, Boone County Solar Β· Clinton Solar, LLC |
80.0 MW | In study |
| Solar project AH1-666, Fleming County Solar Β· Fleming Solar, LLC |
80.0 MW | In study |
| Solar project AH1-665, Fleming County Solar Β· Hummingbird Energy LLC |
80.0 MW | In study |
| Solar + storage project AG2-424, Larue County Solar + storage Β· Magnolia Solar and Grazing Farm LLC |
63.3 MW | In study |
| Solar project AG2-073, Madison County Solar Β· SR Madison, LLC |
53.0 MW | In study |
| Solar project AH1-004, Fayette County Solar Β· SR Fayette, LLC |
40.0 MW | In study |
| Solar project AG2-298, Marion County Solar Β· Crab Run Solar Project, LLC |
35.0 MW | In study |
| Solar project AG2-081, Montgomery County Solar Β· SR Fayette II, LLC |
30.0 MW | In study |
| Solar project AH1-570 Solar Β· South Fork Solar, LLC |
25.0 MW | In study |
| Solar project AH1-571 Solar Β· South Fork Solar, LLC |
20.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)16 Β· 2,235 MW
- PJM (Mid-Atlantic, Midwest)14 Β· 1,802 MW
- MISO (Midcontinent)4 Β· 450 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)