United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Indiana, PJM (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown253,071 MW
Active in queue3,071 MW25 requests
Agreement signed0.0 MW0 requests
Withdrawn172,396 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

25 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AG2-072, Spencer County
Gas Β· Bluegrass Power LLC
700 MWIn study Spencer, INPJM Feb 2025target 2026
Solar project AG2-029, Noble County
Solar Β· Southern Pike Solar LLC
250 MWIn study Noble, INPJM Feb 2025target 2024
Solar project AG2-163, Fountain County
Solar Β· Dolphin Solar LLC
250 MWIn study Fountain, INPJM Feb 2025target 2024
Solar project AG2-245, Starke County
Solar Β· STARKE CENTRAL PROJECT, LLC
210 MWIn study Starke, INPJM Mar 2025target 2023
Solar project AG2-230, St. Joseph County
Solar Β· Dumont Solar, LLC
150 MWIn study St. Joseph, INPJM Mar 2025target 2024
Solar project AG2-637, Randolph County
Solar Β· ACE Development Company, LLC
150 MWIn study Randolph, INPJM Mar 2025target 2025
Solar + storage project AG2-126, Vermillion County
Solar + storage Β· TGE Illinois 211, LLC
150 MWIn study Vermillion, INPJM Mar 2025target 2023
Solar project AG2-491, White County
Solar Β· Black Prairie Solar Park II LLC
100 MWIn study White, INPJM Feb 2025target 2024
Battery storage project AG2-332, Elkhart County
Battery storage Β· Amberjack Solar LLC
100 MWIn study Elkhart, INPJM Feb 2025target 2024
Battery storage project AG2-343, Fountain County
Battery storage Β· Dolphin Solar LLC
100 MWIn study Fountain, INPJM Feb 2025target 2024
Solar project AG2-550, Randolph County
Solar Β· Riverstart Solar Park VI LLC
100 MWIn study Randolph, INPJM Feb 2025target 2024
Battery storage project AG2-248, Elkhart County
Battery storage Β· Amberjack Solar LLC
100 MWIn study Elkhart, INPJM Jan 2025target 2024
Solar project AH1-392, St. Joseph County
Solar Β· ibV Energy Partners LLC
90.0 MWIn study St. Joseph, INPJM Feb 2025target 2025
Battery storage project AH1-482, Pulaski County
Battery storage Β· Lightsource Renewable Energy Development, LLC
78.0 MWIn study Pulaski, INPJM Feb 2025target 2023
Battery storage project AH1-302, Pulaski County
Battery storage Β· Bottlebrush Solar Energy LLC
75.0 MWIn study Pulaski, INPJM Feb 2025target 2025
Solar + storage project AG2-519, Delaware County
Solar + storage Β· Muncie Solar 1, LLC
66.5 MWIn study Delaware, INPJM Mar 2025target 2024
Gas project AG2-562, St. Joseph County
Gas Β· St. Joseph Energy Center, LLC
52.0 MWIn study St. Joseph, INPJM May 2025target 2022
Battery storage project AG2-370, Allen County
Battery storage Β· Tillman Storage LLC
50.0 MWIn study Allen, INPJM Mar 2025target 2024
Battery storage project AG2-551, Randolph County
Battery storage Β· Riverstart Solar Park VI LLC
50.0 MWIn study Randolph, INPJM Feb 2025target 2024
Solar project AH1-153, St. Joseph County
Solar Β· Dumont Solar, LLC
50.0 MWIn study St. Joseph, INPJM Mar 2025target 2025
Battery storage project AG2-345, Fountain County
Battery storage Β· Dolphin Solar LLC
50.0 MWIn study Fountain, INPJM Feb 2025target 2024
Battery storage project AG2-014, White County
Battery storage Β· Black Prairie Storage LLC
50.0 MWIn study White, INPJM Feb 2025target 2023
Battery storage project AG2-492, White County
Battery storage Β· Black Prairie Storage II LLC
50.0 MWIn study White, INPJM Feb 2025target 2024
Solar + storage project AG2-191, Grant County
Solar + storage Β· BR Solar Sheriff 2 LLC
30.0 MWIn study Grant, INPJM Feb 2025target 2023
Solar + storage project AG2-192, Grant County
Solar + storage Β· BR Solar Sheriff 2 LLC
19.0 MWIn study Grant, INPJM Feb 2025target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)