Interconnection queue in NYISO (New York) (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6749 MW
Active in queue749 MW6 requests
Agreement signed0.0 MW0 requests
Withdrawn612,565 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Alle Catt II Wind
Onshore wind Β· Alle-Catt Wind Energy LLC
339 MWIn study Cattaraugus, NYNYISO Jan 2017target 2026
Gateway Solar Energy Center
Solar Β· Gateway Solar Energy Center, LLC
180 MWIn study St. Lawrence, NYNYISO Mar 2017target 2028
Flint Mine Solar
Solar Β· Flint Mine Solar LLC
100 MWIn study Greene, NYNYISO Jun 2017target 2026
Columbia County 1
Solar Β· Hecate Energy Columbia County 1, LLC
60.0 MWIn study Columbia, NYNYISO Jul 2017target 2027
Watkins Glen Solar
Solar Β· Watkins Glen Solar Energy Center, LLC
50.0 MWIn study Schuyler, NYNYISO Mar 2017target 2028
SunEast Skyline Solar LLC
Solar Β· SunEast Skyline Solar LLC
20.0 MWIn study Oneida, NYNYISO Sep 2017target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)