Completed queue projects in NYISO (New York) (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10633 MW
Active in queue370 MW13 requests
Agreement signed0.0 MW0 requests
Withdrawn252,046 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Bluestone Wind
Onshore wind Β· Bluestone Wind, LLC
112 MWOperating NYNYISO Sep 2016
Bluestone Wind
Onshore wind Β· Bluestone Wind, LLC
112 MWOperating Broome, NYNYISO Sep 20162023
Number 3 Wind Energy
Onshore wind Β· Number Three Wind LLC
104 MWOperating Lewis, NYNYISO Jan 20162023
Number 3 Wind Energy
Onshore wind Β· Number Three Wind LLC
104 MWOperating NYNYISO Jan 2016
Roaring Brook Wind
Onshore wind Β· PPM Roaring Brook, LLC
79.7 MWOperating Lewis, NYNYISO May 20162022
Roaring Brook Wind
Onshore wind Β· PPM Roaring Brook, LLC
79.7 MWOperating NYNYISO May 2016
Albany County 1
Solar Β· Hecate Energy Albany 1 LLC
20.0 MWOperating Albany, NYNYISO Aug 2016
Albany County 1
Solar Β· Hecate Energy Albany 1 LLC
20.0 MWOperating NYNYISO Aug 2016
Fulton
Hydro Β· Erie Boulevard Hydropower, LP
1.3 MWOperating Oswego, NYNYISO Oct 20162018
Fulton
Hydro Β· Erie Boulevard Hydropower, LP
1.3 MWOperating NYNYISO Oct 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)