Withdrawn queue requests in New Jersey, NYISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown103,789 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn103,789 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Liberty BESS
Battery storage Β· North Bergen Liberty Generating LLC
1,200 MWWithdrawn / abandoned Hudson, NJNYISO Sep 2024
Liberty BESS
Battery storage Β· North Bergen Liberty Generating
600 MWWithdrawn / abandoned Hudson, NJNYISO May 2023
Bayonne Energy Storage I
Battery storage Β· AMBAR POWER HOLDCO LLC
600 MWWithdrawn / abandoned Hudson, NJNYISO Oct 2024
Bayonne Energy Storage II
Battery storage Β· AMBAR POWER HOLDCO LLC
400 MWWithdrawn / abandoned Hudson, NJNYISO Oct 2024
Bayone Energy Center II
Gas Β· Hess Corporation
250 MWWithdrawn / abandoned Hudson, NJNYISO Jun 2007
Linden Cogen Uprate
Gas Β· East Coast Power LLC
234 MWWithdrawn / abandoned Union, NJNYISO Oct 2015
Linden Cogen Uprate
Gas Β· East Coast Power LLC
208 MWWithdrawn / abandoned Union, NJNYISO Mar 2013
Brunswick Energy Storage
Battery storage Β· East Coast Power LLC
165 MWWithdrawn / abandoned Union, NJNYISO Sep 2021
Brunswick Energy Storage
Battery storage Β· JERA Americas Inc.
100 MWWithdrawn / abandoned Union, NJNYISO Oct 2019
Linden Cogen Uprate
Gas Β· East Coast Power LLC
32.0 MWWithdrawn / abandoned Union, NJNYISO Sep 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)