United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8688 MW
Active in queue688 MW8 requests
Agreement signed688 MW8 requests
Withdrawn5317.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J476, Atchison County
Onshore wind
246 MWAgreement signed Atchison, MOMISO Sep 2015target 2021
Solar project J483, Liberty County
Solar
100 MWAgreement signed Liberty, TXMISO Sep 20152024
Solar project J524, Webster County
Solar
100 MWAgreement signed Webster, IAMISO Nov 20152022
Gas project J514, Marshall County
Gas
65.0 MWAgreement signed Marshall, IAMISO Nov 2015target 2017
Solar project J504, Linn County
Solar
50.0 MWAgreement signed Linn, IAMISO Nov 20152024
Solar project J523, Mower County
Solar
50.0 MWAgreement signed Mower, MNMISO Nov 20152024
Gas project J485, Olmsted County
Gas
46.9 MWAgreement signed Olmsted, MNMISO Oct 20152018
Battery storage project J466, Huron County
Battery storage
30.0 MWAgreement signed Huron, MIMISO May 2015target 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)