United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Hydro interconnection queue in MISO (Midcontinent)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5110 MW
Active in queue110 MW5 requests
Agreement signed87.0 MW2 requests
Withdrawn4264 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project J1213, Iron County
Hydro
60.0 MWAgreement signed Iron, MOMISO Apr 2019target 2024
Hydro project E291
Hydro
27.0 MWAgreement signed TXMISO May 20122020
Hydro project J4200, Ramsey County
Hydro
16.0 MWIn study Ramsey, MNMISO Sep 2025target 2008
Hydro project J1826, Dakota County
Hydro
4.0 MWIn study Dakota, MNMISO Sep 2022target 2024
Hydro project J3219, Dakota County
Hydro
3.0 MWIn study Dakota, MNMISO Sep 2022target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)