United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in ISO-NE (New England) (2018 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Offshore Wind Offshore wind |
827 MW | In study |
| Revoultion Offshore wind Offshore wind |
704 MW | Agreement signed |
| Ocean State Power uprate Gas |
73.2 MW | Agreement signed |
| FPS Panton Solar Solar |
50.0 MW | Agreement signed |
| Solar Solar |
6.8 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)68 Β· 16.4 GW
- MISO (Midcontinent)61 Β· 10.3 GW
- PJM (Mid-Atlantic, Midwest)68 Β· 10.1 GW
- ERCOT (Texas)45 Β· 9,218 MW
- SPP (Southwest Power Pool)42 Β· 6,803 MW
- CAISO (California)23 Β· 6,790 MW
- NYISO (New York)15 Β· 3,444 MW
- Southeast (non-ISO utilities)21 Β· 2,381 MW
- ISO-NE (New England)5 Β· 1,661 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)