OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in ISO-NE (New England) (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3831 MW
Active in queue831 MW3 requests
Agreement signed831 MW3 requests
Withdrawn424,856 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Park City Offshore Wind
Offshore wind
791 MWAgreement signed MAISO-NE Dec 2017target 2029
Fair Haven Solar
Solar
20.0 MWAgreement signed Rutland, VTISO-NE Aug 2017target 2027
Shaftsbury Solar
Solar
20.0 MWAgreement signed Bennington, VTISO-NE Jul 2017target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)