OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New York, ISO-NE

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown42,500 MW
Active in queue470 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn42,500 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
New Scotland BESS (NYISO-C24-045)
Battery storage
1,350 MWWithdrawn / abandoned Albany, NYISO-NE Dec 2024target 2027
Dover NY BESS (NYISO-C24-316)
Battery storage
1,000 MWWithdrawn / abandoned Dutchess, NYISO-NE Dec 2024target 2028
Zenobe Rotterdam LLC (NYISO-C24-191)
Battery storage
100 MWWithdrawn / abandoned Schenectady, NYISO-NE Dec 2024target 2028
Chazy Lake BESS (NYISO-C24-308)
Battery storage
50.0 MWWithdrawn / abandoned Clinton, NYISO-NE Dec 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)