Completed queue projects in ERCOT (Texas) (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown234,354 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn246,711 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

23 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Bac
Gas Β· PHR Holdings
390 MWOperating ERCOT Oct 20122018
Ector County Energy Center G
Gas Β· Invenergy
341 MWOperating ERCOT Nov 20122015
Jumbo Road Wind
Onshore wind Β· TX Jumbo Road Wind, LLC
300 MWOperating ERCOT Oct 20122015
BTE (Baytown Chiller)
Gas Β· Calpine
270 MWOperating ERCOT Jul 20122018
Goodnight Wind
Onshore wind Β· FGE Goodnight I, LLC
258 MWOperating Armstrong, TXERCOT Jul 20122024
Redgate G
Gas Β· STEC
225 MWOperating ERCOT Dec 20122016
Panhandle Wind 1
Onshore wind Β· Pattern Panhandle Wind, LLC
218 MWOperating ERCOT Jul 20122014
Logans Gap Wind I
Onshore wind Β· Pattern Energy
211 MWOperating ERCOT Feb 20122015
South Plains I
Onshore wind Β· SunEdison
200 MWOperating ERCOT Apr 20122015
Hereford Wind
Onshore wind Β· EDF Renewables
200 MWOperating ERCOT Oct 20122015
Longhorn North
Onshore wind Β· EDF Renewables
200 MWOperating ERCOT Mar 20122015
Los Vientos III
Onshore wind Β· Duke Energy
200 MWOperating ERCOT Apr 20122015
Panhandle Wind 2
Onshore wind Β· Pattern Panhandle Wind 2, LLC
182 MWOperating ERCOT Jul 20122014
Spinning Spur Wind Two
Onshore wind Β· Cielo Wind Services
161 MWOperating ERCOT Jan 20122014
Fluvanna
Onshore wind Β· Terna Energy
155 MWOperating ERCOT Jun 20122017
South Plains II Phase a
Onshore wind Β· SunEdison
152 MWOperating ERCOT Apr 20122016
Route 66 Wind
Onshore wind Β· First Wind
150 MWOperating ERCOT Jul 20122015
South Plains II Phase b
Onshore wind Β· SunEdison
149 MWOperating ERCOT Apr 20122016
Fegc
Gas Β· Friendswood Energy Genco
129 MWOperating ERCOT Feb 20122018
Los Vientos V
Onshore wind Β· Duke Energy
110 MWOperating ERCOT Jul 20122016
Windthorst 2
Onshore wind Β· OwnEnergy
65.0 MWOperating ERCOT Jun 20122014
OCI Alamo 1
Solar Β· OCI Alamo 1 LLC
50.0 MWOperating ERCOT Aug 20122013
OCI Alamo 4 (Brackettville / ECLIPSE)
Solar Β· OCI Solar Power LLC
38.0 MWOperating ERCOT Mar 20122014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)