OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Nevada, CAISO (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown96,576 MW
Active in queue6,576 MW9 requests
Agreement signed3,838 MW4 requests
Withdrawn2730 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Mosey
Solar + storage
1,081 MWAgreement signed Clark, NVCAISO Apr 2021target 2029
Water Rock Solar 2
Solar + storage
1,034 MWIn study Nye, NVCAISO Apr 2021target 2028
Silver Star Solar
Solar + storage
1,034 MWAgreement signed Nye, NVCAISO Apr 2021target 2028
Rock Valley Energy Center
Solar + storage
1,024 MWAgreement signed Nye, NVCAISO Apr 2021target 2029
Kawich
Solar + storage
700 MWAgreement signed Clark, NVCAISO Apr 2021target 2029
Larrea Solar
Solar + storage
614 MWIn study Clark, NVCAISO Apr 2021target 2028
Sterling
Solar + storage
500 MWIn study Clark, NVCAISO Apr 2021target 2031
Dandelion Hybrid Solar
Solar + storage
334 MWIn study Nye, NVCAISO Apr 2021target 2027
Delamar Energy Storage 2
Battery storage
256 MWIn study Clark, NVCAISO Apr 2021target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)