OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 7 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Rainbow Energy Center
Gas
523 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2018
Arizona Mohave Solar
Solar
521 MWWithdrawn / abandoned Mohave, AZCAISO May 2016target 2020
Lockhart 4 Energy Storage
Battery storage
520 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Baca Solar
Battery storage
520 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Sonoran 2
Solar
520 MWWithdrawn / abandoned Riverside, CACAISO Mar 2003target 2021
Harquahala Solar
Solar
519 MWWithdrawn / abandoned Maricopa, AZCAISO May 2016target 2021
Cedro
Solar + storage
519 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Carranza
Solar + storage
519 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Palmera
Solar + storage
519 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Vegas Valley
Solar + storage
519 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Midas Energy Storage
Battery storage
518 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Temescal Canyon Energy Storage
Battery storage
518 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Frates Energy Storage
Battery storage
518 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Vulcan Tertius
Solar + storage
518 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Fritts
Solar + storage
517 MWWithdrawn / abandoned Fresno, CACAISO Apr 2023target 2029
Victorious
Battery storage
516 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2023target 2028
Bellhop
Battery storage
516 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Olympic
Battery storage
515 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Stocker Storage
Battery storage
515 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Fresa
Battery storage
515 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Connor
Battery storage
515 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2023target 2030
Appellation
Battery storage
515 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Pinecone
Battery storage
515 MWWithdrawn / abandoned Yuma, AZCAISO Apr 2023target 2028
Finn Wind
Onshore wind
514 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Broadcast
Battery storage
514 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Dogwood Wind
Onshore wind
514 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Chirock
Battery storage
514 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Yerba Santa
Battery storage
514 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Skydive
Battery storage
514 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Silvercoin
Battery storage
514 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Greenwood Energy Storage 2
Battery storage
513 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Thar Energy Storage
Battery storage
513 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Moeras Energy Storage
Battery storage
513 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Rock Daisy
Solar + storage
513 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Valhalla Energy Storage
Battery storage
513 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
MT Baldy Energy Storage
Battery storage
513 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2031
Menilles
Solar + storage
511 MWWithdrawn / abandoned Fresno, CACAISO Apr 2021target 2024
Kilowatt Ranch
Battery storage
511 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Blythe BESS
Battery storage
510 MWWithdrawn / abandoned Riverside, CACAISO Mar 2021target 2022
Transcanada Peaker
Gas
510 MWWithdrawn / abandoned San Bernardino, CACAISO Nov 2006target 2011
Rockfish Storage 1
Battery storage
510 MWWithdrawn / abandoned Monterey, CACAISO Apr 2018target 2023
Rockfish Storage 2
Battery storage
510 MWWithdrawn / abandoned Monterey, CACAISO Apr 2018target 2024
Grisedale Storage 1
Battery storage
510 MWWithdrawn / abandoned Riverside, CACAISO Apr 2020target 2022
Goodall Storage
Battery storage
510 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2023
Solar Four
Solar
510 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2017
Dolores
Battery storage
510 MWWithdrawn / abandoned San Clara, CACAISO Apr 2021target 2025
Rex Solaris 2
Solar + storage
509 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Rex Solaris 1
Solar + storage
509 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Pinnacle Heights
Solar + storage
508 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Stockton Generation
Gas
508 MWWithdrawn / abandoned San Joaquin, CACAISO Feb 2007target 2014
Page 7 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)