United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) (2022 requests) โ€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31799.9 GW
Active in queue99.9 GW317 requests
Agreement signed12.2 GW66 requests
Withdrawn494132.6 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

317 requests ยท page 5 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project PIS025, Utah County
Battery storage
199 MWIn study Utah, UTWest Jul 2022target 2025
Battery storage project C2-178, Crook County
Battery storage ยท Oathkeeper Storage, LLC
199 MWAgreement signed Crook, ORWest May 2022target 2032
Battery storage project C2-170, Lake County
Battery storage
199 MWIn study Lake, ORWest May 2022target 2026
Onshore wind project Company NO, Storey County
Onshore wind
190 MWPaused / redesign Storey, NVWest Mar 2022target 2026
Battery storage project 146, Pima County
Battery storage
175 MWIn study Pima, AZWest Dec 2022target 2026
Solar + storage project C2-156, Linn County
Solar + storage ยท Sand Ridge PV I, LLC
175 MWPaused / redesign Linn, ORWest May 2022target 2028
Solar + storage project C2-99, Emery County
Solar + storage
166 MWIn study Emery, UTWest May 2022target 2026
Battery storage project Q479, Maricopa County
Battery storage
165 MWIn study Maricopa, AZWest Sep 2022target 2028
Other project G0794, Linn County
Other
160 MWIn study Linn, ORWest Aug 2022target 2028
Other project G0793, Linn County
Other
160 MWIn study Linn, ORWest Aug 2022target 2028
Battery storage project 22, Sacramento County
Battery storage
160 MWIn study Sacramento, CAWest Jul 2022target 2027
Solar + storage project 30, Sacramento County
Solar + storage
156 MWIn study Sacramento, CAWest Dec 2022target 2029
Onshore wind project C2-91, Bonneville County
Onshore wind ยท PacifiCorp
153 MWIn study Bonneville, IDWest May 2022target 2026
Solar + storage project 2022-G11, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Aug 2022target 2025
Battery storage project 147, Pima County
Battery storage
150 MWIn study Pima, AZWest Dec 2022target 2026
Onshore wind project C2-49, Converse County
Onshore wind
150 MWIn study Converse, WYWest May 2022target 2026
Solar + storage project BHCT G35, Pueblo County
Solar + storage
150 MWIn study Pueblo, COWest Aug 2022target 2026
Solar + storage project 2022-G10, Pinal County
Solar + storage
150 MWIn study Pinal, AZWest Jul 2022target 2025
Battery storage project 639, Ada County
Battery storage ยท Idaho Power Companyโ€šร„รฎPower Supply
150 MWAgreement signed Ada, IDWest Feb 2022target 2026
Battery storage project 640, Ada County
Battery storage ยท Idaho Power Companyโ€šร„รฎPower Supply
150 MWPaused / redesign Ada, IDWest Feb 2022target 2026
Battery storage project 27, Sacramento County
Battery storage
150 MWIn study Sacramento, CAWest Oct 2022target 2027
Solar project PIS027, Utah County
Solar
150 MWIn study Utah, UTWest Jul 2022target 2025
Solar + storage project 2023-G2
Solar + storage
150 MWIn study West Nov 2022target 2026
Solar project 2023-G3
Solar
150 MWIn study West Nov 2022target 2026
Solar + storage project Q463, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Mar 2022target 2024
Battery storage project 122, Pinal County
Battery storage
150 MWIn study Pinal, AZWest May 2022target 2026
Battery storage project 22-110, Marion County
Battery storage
150 MWIn study Marion, ORWest Apr 2022target 2028
Battery storage project 132, Pima County
Battery storage
150 MWIn study Pima, AZWest Jul 2022target 2025
Battery storage project Company 216, Clark County
Battery storage
150 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Battery storage project 22-111, Multnomah County
Battery storage
150 MWIn study Multnomah, ORWest Nov 2022target 2028
Solar project 636, Elmore County
Solar ยท Soles Rest Solar LLC
149 MWAgreement signed Elmore, IDWest Feb 2022target 2028
Battery storage project C2-79, Linn County
Battery storage ยท Creekside Storage LLC
145 MWPaused / redesign Linn, ORWest May 2022target 2025
Solar + storage project 654, Bingham County
Solar + storage ยท Pingree Solar LLC
130 MWPaused / redesign Bingham, IDWest May 2022target 2028
Solar + storage project GI-2022-163, Riverside County
Solar + storage
125 MWIn study Riverside, CAWest Sep 2022target 2025
Solar project C2-167, Emery County
Solar ยท PacifiCorp
125 MWIn study Emery, UTWest May 2022target 2026
Gas project CLPT G22, Laramie County
Gas ยท Black Hills Electric Generation, LLC
115 MWAgreement signed Laramie, WYWest Nov 2022target 2024
Solar project S0002, Carbon County
Solar ยท PacifiCorp
111 MWIn study Carbon, WYWest Mar 2022target 2025
Solar project BHBE G23, Oglala Lakota County
Solar
110 MWAgreement signed Oglala Lakota, SDWest Nov 2022target 2026
Battery storage project Company NH, Washoe County
Battery storage
100 MWPaused / redesign Washoe, NVWest Mar 2022target 2024
Battery storage project C2-204, Yakima County
Battery storage
100 MWIn study Yakima, WAWest May 2022target 2024
Battery storage project Company 221, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Battery storage project Company 222, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Mar 2022target 2029
SS100S
Solar
100 MWAgreement signed El Paso, TXWest Sep 2022target 2025
Solar + storage project GI-2022-154, Imperial County
Solar + storage
100 MWIn study Imperial, CAWest Feb 2022target 2024
Other project 115, Pima County
Other
100 MWIn study Pima, AZWest Mar 2022target 2025
Battery storage project C2-27, Multnomah County
Battery storage ยท Troutdale Grid, LLC
100 MWAgreement signed Multnomah, ORWest Apr 2022target 2028
Battery storage project IA-PNM-2022-11, Bernalillo County
Battery storage
100 MWIn study Bernalillo, NMWest Apr 2022target 2024
Battery storage project G0828, Grant County
Battery storage
100 MWIn study Grant, WAWest Dec 2022target 2026
Other project 116, Pima County
Other
100 MWIn study Pima, AZWest Mar 2022target 2025
Battery storage project 25, Sacramento County
Battery storage
100 MWIn study Sacramento, CAWest Aug 2022target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)