Withdrawn queue requests in the USA — page 433

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 433 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 22-07254, Weld County
Battery storage
10.0 MWWithdrawn / abandoned Weld, COWest Jul 2022target 2026
Other project G0399, Morrow County
Other
10.0 MWWithdrawn / abandoned Morrow, ORWest Dec 2009target 2010
Solar project IC-533, Autauga County
Solar
10.0 MWWithdrawn / abandoned Autauga, ALSoutheast Nov 2016
Solar project Z1-122, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Onshore wind project 380, Morrow / Umatilla County
Onshore wind
10.0 MWWithdrawn / abandoned Morrow / Umatilla, ORWest Mar 2011target 2012
Solar project AG1-206, Jefferson County
Solar
10.0 MWWithdrawn / abandoned Jefferson, PAPJM Sep 2020target 2022
Solar project IC-528, Pickens County
Solar
10.0 MWWithdrawn / abandoned Pickens, ALSoutheast Nov 2016
Solar project W2-069, Centre County
Solar
10.0 MWWithdrawn / abandoned Centre, PAPJM Jul 2010target 2012
Hydro project 350, Jackson County
Hydro
10.0 MWWithdrawn / abandoned Jackson, ORWest Sep 2010target 2012
Solar project X2-098, Warren County
Solar
10.0 MWWithdrawn / abandoned Warren, NJPJM Jul 2011target 2013
Solar project 4598, Florence County
Solar
10.0 MWWithdrawn / abandoned Florence, SCSoutheast Oct 2015
Solar project X2-091, Cook County
Solar
10.0 MWWithdrawn / abandoned Cook, ILPJM Jul 2011target 2013
Solar project Z1-126, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2016
Onshore wind project G0474, Wasco County
Onshore wind
10.0 MWWithdrawn / abandoned Wasco, ORWest May 2012target 2013
Solar project 475, Malheur County
Solar
10.0 MWWithdrawn / abandoned Malheur, ORWest Mar 2015
Solar project AB2-056, Cecil County
Solar
10.0 MWWithdrawn / abandoned Cecil, MDPJM Mar 2016target 2018
Solar project AH2-318, Warren County
Solar
10.0 MWWithdrawn / abandoned Warren, PAPJM Mar 2022target 2024
Albatross FIS application fee
Other · Albatross Solar, LLC
10.0 MWWithdrawn / abandoned Mclennan, TXERCOT target 2026
Solar + storage project C3-073, Box Elder County
Solar + storage
10.0 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2024
Hydro project 27, Spokane County
Hydro
10.0 MWWithdrawn / abandoned Spokane, WAWest Oct 2009target 2012
Solar project Company 108, Clark County
Solar
10.0 MWWithdrawn / abandoned Clark, NVWest May 2011target 2013
Solar project X2-016, Gloucester County
Solar
10.0 MWWithdrawn / abandoned Gloucester, NJPJM May 2011target 2013
Battery storage project 20200921002, Hampton County
Battery storage
10.0 MWWithdrawn / abandoned Hampton, SCSoutheast target 2021
Solar project AG2-353, Erie County
Solar
10.0 MWWithdrawn / abandoned Erie, PAPJM Mar 2021target 2023
Solar project 4697, Florence County
Solar
10.0 MWWithdrawn / abandoned Florence, SCSoutheast Nov 2015
Hydro project 27, King County
Hydro
10.0 MWWithdrawn / abandoned King, WAWest Aug 2010target 2013
Battery storage project Q304, Maricopa County
Battery storage
10.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2019target 2020
Solar project 847, Sweetwater County
Solar
10.0 MWWithdrawn / abandoned Sweetwater, WYWest Jan 2017target 2018
Jayne East
Solar
10.0 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2014
Battery storage project Z2-095, Sussex County
Battery storage
10.0 MWWithdrawn / abandoned Sussex, NJPJM Apr 2014target 2015
Andover Solar Farm
Solar
10.0 MWWithdrawn / abandoned Sussex, NJPJM Oct 2011target 2015
Onshore wind project G0232, Wasco County
Onshore wind
10.0 MWWithdrawn / abandoned Wasco, ORWest Aug 2006target 2007
Battery storage project 589, Morgan County
Battery storage
10.0 MWWithdrawn / abandoned Morgan, TNSoutheast Nov 2023
Cloverleaf Solar Farm
Solar
10.0 MWWithdrawn / abandoned Monmouth, NJPJM Jun 2011target 2014
Solar project AG2-232, Franklin County
Solar
10.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2021target 2023
Solar project AH1-501, Forest County
Solar
10.0 MWWithdrawn / abandoned Forest, PAPJM Sep 2021target 2024
Solar project 662, Klamath County
Solar
10.0 MWWithdrawn / abandoned Klamath, ORWest Apr 2015target 2016
Hydro project U1-074, Fayette County
Hydro
10.0 MWWithdrawn / abandoned Fayette, PAPJM Apr 2008target 2015
Solar project AG1-242, Clearfield County
Solar
10.0 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2020target 2022
Solar project 1003, Tooele County
Solar
10.0 MWWithdrawn / abandoned Tooele, UTWest Feb 2018target 2019
Other project GI-0614b, Morton County
Other
10.0 MWWithdrawn / abandoned Morton, NDWest Sep 2006
Solar project AG2-434, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2021target 2023
Onshore wind project 121, Judith Basin County
Onshore wind
10.0 MWWithdrawn / abandoned Judith Basin, MTWest Aug 2010target 2011
Solar + storage project G0764, Union County
Solar + storage
10.0 MWWithdrawn / abandoned Union, ORWest Jul 2022target 2026
Solar project 477, Malheur County
Solar
10.0 MWWithdrawn / abandoned Malheur, ORWest Mar 2015
Solar project AD1-027, Camden County
Solar
10.0 MWWithdrawn / abandoned Camden, NJPJM Jul 2017target 2017
Double Tollgate Solar Project
Solar
10.0 MWWithdrawn / abandoned Clarke, VAPJM Apr 2017target 2023
Gas project AB1-157, Marshall County
Gas
10.0 MWWithdrawn / abandoned Marshall, WVPJM Oct 2015target 2018
Foster Run
Solar
10.0 MWWithdrawn / abandoned Venango, PAPJM Sep 2020target 2026
Solar project AB2-033, Accomack County
Solar
10.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2016target 2017
Page 433 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)