Requests shown19245.5 GW
Active in queue45.5 GW192 requests
Agreement signed1,964 MW16 requests
Withdrawn23746.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

192 requests Β· page 4 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project PIS092, Utah County
Gas Β· PacifiCorp
73.0 MWIn study Utah, UTWest Oct 2024target 2026
Gas project PIS093, Juab County
Gas Β· PacifiCorp
71.0 MWIn study Juab, UTWest Oct 2024target 2026
Solar project PIS058, Emery County
Solar Β· PacifiCorp
70.0 MWIn study Emery, UTWest May 2024target 2026
Gas project PIS090, Utah County
Gas Β· PacifiCorp
62.0 MWIn study Utah, UTWest Oct 2024target 2026
Battery storage project S0029, Crook County
Battery storage
60.8 MWIn study Crook, ORWest Feb 2024target 2026
Battery storage project S0030, Crook County
Battery storage
55.0 MWIn study Crook, ORWest Feb 2024target 2026
Battery storage project 24-242, Polk County
Battery storage
50.0 MWIn study Polk, ORWest Apr 2024target 2028
Gas project 2024-G6, Mohave County
Gas
50.0 MWIn study Mohave, AZWest Aug 2024target 2027
Battery storage project BHCT G50, Pueblo County
Battery storage Β· Black Hills Colorado Electric, LLC
50.0 MWIn study Pueblo, COWest Jun 2024target 2026
AN50B
Battery storage
50.0 MWAgreement signed Luna, NMWest Mar 2024target 2027
Solar + storage project 2024-G1, Mohave County
Solar + storage
50.0 MWIn study Mohave, AZWest Jan 2024target 2027
Other project Q550, Maricopa County
Other
43.0 MWIn study Maricopa, AZWest Apr 2024target 2028
Other project Q549, Maricopa County
Other
42.1 MWIn study Maricopa, AZWest Apr 2024target 2026
Onshore wind project PIS051, Converse County
Onshore wind Β· PacifiCorp
42.0 MWIn study Converse, WYWest Feb 2024target 2024
Solar project CS24-14, Spokane County
Solar
40.0 MWAgreement signed Spokane, WAWest Apr 2024target 2028
Onshore wind project PIS052, Carbon County
Onshore wind Β· PacifiCorp
30.0 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project PIS053, Carbon County
Onshore wind Β· PacifiCorp
28.0 MWIn study Carbon, WYWest Feb 2024target 2024
Onshore wind project PIS050, Carbon County
Onshore wind Β· PacifiCorp
26.0 MWIn study Carbon, WYWest Feb 2024target 2024
Geothermal project Company RA, Pershing County
Geothermal
20.0 MWIn study Pershing, NVWest Oct 2024target 2029
Solar project G1069, Harney County
Solar
20.0 MWIn study Harney, ORWest Jul 2024target 2025
Geothermal project Company RB, Lander County
Geothermal
20.0 MWIn study Lander, NVWest Oct 2024target 2029
Solar + storage project PIS098, Jefferson County
Solar + storage Β· PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Solar + storage project PIS094, Jefferson County
Solar + storage Β· PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Solar project PIS099, Jefferson County
Solar Β· PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Solar project PIS095, Jefferson County
Solar Β· PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Gas project PIS091, Salt Lake County
Gas Β· PacifiCorp
17.0 MWIn study Salt Lake, UTWest Oct 2024target 2026
Battery storage project G1064, Umatilla County
Battery storage
15.0 MWIn study Umatilla, ORWest Apr 2024target 2026
Hydro project 458, Broadwater County
Hydro
10.4 MWIn study Broadwater, MTWest Apr 2024
Battery storage project GI-2024-08, Pueblo County
Battery storage
10.0 MWIn study Pueblo, COWest May 2024target 2026
Solar project 24-10021, Larimer County
Solar
10.0 MWIn study Larimer, COWest Oct 2024target 2026
Onshore wind project PIS054, Carbon County
Onshore wind Β· PacifiCorp
6.6 MWIn study Carbon, WYWest Feb 2024target 2024
Gas project 456, Brown County
Gas
5.0 MWIn study Brown, SDWest Feb 2024target 2025
Solar project 752, Malheur County
Solar Β· Fry Foods Inc.
4.2 MWAgreement signed Malheur, ORWest Aug 2024target 2025
Hydro project 457, Lewis And Clark County
Hydro
2.2 MWIn study Lewis And Clark, MTWest Mar 2024target 2025
Gas project 462, Beadle County
Gas
2.0 MWIn study Beadle, SDWest Jun 2024target 2025
Solar project CS24-07, Adams County
Solar
2.0 MWAgreement signed Adams, WAWest Apr 2024target 2026
Solar project CS24-01, Adams County
Solar
1.0 MWAgreement signed Adams, WAWest Mar 2024target 2024
Solar project G1068, Clark County
Solar
1.0 MWIn study Clark, WAWest Jun 2024target 2024
Solar project G1071, Deschutes County
Solar
1.0 MWIn study Deschutes, ORWest Oct 2024target 2025
Gas project 463, Beadle County
Gas
0.5 MWIn study Beadle, SDWest Jun 2024target 2025
Battery storage project CS24-02, Spokane County
Battery storage
0.5 MWAgreement signed Spokane, WAWest Apr 2024target 2025
Solar project G1066, Marion County
Solar
0.4 MWIn study Marion, ORWest Apr 2024target 2024
Page 4 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)