United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 372

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 372 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 1228, Sweetwater County
Solar + storage
20.0 MWWithdrawn / abandoned Sweetwater, WYWest May 2020target 2023
Solar project V4-063, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Jan 2010target 2011
Solar project Company GS, Douglas County
Solar
20.0 MWWithdrawn / abandoned Douglas, NVWest Apr 2015target 2016
Solar project Q22, Pinal County
Solar
20.0 MWWithdrawn / abandoned Pinal, AZWest Dec 2010target 2012
Battery storage project Y2-048, Dekalb County
Battery storage
20.0 MWWithdrawn / abandoned Dekalb, ILPJM Aug 2012target 2013
Solar project GI-2011-6, Boulder County
Solar
20.0 MWWithdrawn / abandoned Boulder, COWest Jul 2011target 2012
Glenwood Battery Storage
Battery storage · LI Energy Storage System
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Mar 2015
Solar project G0533, Wasco County
Solar
20.0 MWWithdrawn / abandoned Wasco, ORWest Apr 2016target 2019
Sun Harvester Solar Project
Solar
20.0 MWWithdrawn / abandoned Fresno, CACAISO Feb 2010target 2012
ELP Chatham Storage
Battery storage · ELP Chatham Storage LLC
20.0 MWWithdrawn / abandoned Columbia, NYNYISO Nov 2022
Solar project IC-293, Dodge County
Solar
20.0 MWWithdrawn / abandoned Dodge, GASoutheast Apr 2013
Sithe Independence BESS
Battery storage · Vistra Operations Company, LLC
20.0 MWWithdrawn / abandoned Oswego, NYNYISO Nov 2019
Cayuga Energy Storage
Battery storage · AES Energy Storage, LLC
20.0 MWWithdrawn / abandoned Onondaga, NYNYISO Dec 2008
Solar project Q101, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Feb 2010target 2012
Solar project AG2-265, Fayette County
Solar
20.0 MWWithdrawn / abandoned Fayette, OHPJM Mar 2021target 2023
Friendship Solar Farm
Solar + storage · Apalachin Solar LLC
20.0 MWWithdrawn / abandoned Allegany, NYNYISO Sep 2022
Onshore wind project G818, Grant County
Onshore wind
20.0 MWWithdrawn / abandoned Grant, MNMISO Jul 2007
Shortsville Solar
Solar · Shortsville Solar Center, LLC
20.0 MWWithdrawn / abandoned Ontario, NYNYISO Aug 2014
Solar project W2-054, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Jul 2010target 2012
Florence solar
Solar
20.0 MWWithdrawn / abandoned Burlington, NJPJM Jul 2010target 2014
Solar + storage project AG1-545, Prince George County
Solar + storage
20.0 MWWithdrawn / abandoned Prince George, VAPJM Sep 2020target 2024
Fuller Storage
Battery storage · Granada Solar, LLC
20.0 MWWithdrawn / abandoned Orange, NYNYISO Sep 2024
Clay Solar
Solar · SED NY Holdings LLC
20.0 MWWithdrawn / abandoned Onondaga, NYNYISO Sep 2017
Cal SP Xii
Solar
20.0 MWWithdrawn / abandoned Merced, CACAISO Jul 2010target 2012
Re Willow Springs
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2014
Solar project IC-307, Pierce County
Solar
20.0 MWWithdrawn / abandoned Pierce, GASoutheast Jul 2013
Re Goldtown
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2014
Onshore wind project GEN-2010-025, Benton County
Onshore wind
20.0 MWWithdrawn / abandoned Benton, ARSPP Mar 2010target 2010
Solar project Company 142, Clark County
Solar
20.0 MWWithdrawn / abandoned Clark, NVWest Apr 2013target 2015
East Hampton - Phase 3
Solar · East Hampton Solar Farm 2, LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2014
Solar project 452, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Onshore wind project MPC01100, Cass County
Onshore wind
20.0 MWWithdrawn / abandoned Cass, NDMISO Mar 2008target 2008
Solar project 759, Klamath County
Solar
20.0 MWWithdrawn / abandoned Klamath, ORWest Jun 2016target 2017
McKean Solar 1 - 20 MW
Solar · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PAPJM Feb 2025target 2024
Solar project AA2-056, Halifax County
Solar
20.0 MWWithdrawn / abandoned Halifax, NCPJM Feb 2015target 2016
Solar project IC-360, Colquitt County
Solar
20.0 MWWithdrawn / abandoned Colquitt, GASoutheast Apr 2014
Battery storage project AA2-129, Accomack County
Battery storage
20.0 MWWithdrawn / abandoned Accomack, VAPJM Apr 2015target 2016
Solar project IC-266, Early County
Solar
20.0 MWWithdrawn / abandoned Early, GASoutheast Mar 2012
Solar project W3-164, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Oct 2010target 2011
Solar project AE2-252, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Mar 2019target 2021
Solar project 312, Iron County
Solar
20.0 MWWithdrawn / abandoned Iron, UTWest Dec 2009target 2010
Solar project 668, Jefferson County
Solar
20.0 MWWithdrawn / abandoned Jefferson, IDWest May 2015target 2016
Other project 361, Malheur County
Other
20.0 MWWithdrawn / abandoned Malheur, ORWest Jan 2011
Solar project AG1-081, Isle Of Wight County
Solar
20.0 MWWithdrawn / abandoned Isle Of Wight, VAPJM Jul 2020target 2021
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2022target 2024
Solar + storage project J1738, Mcpherson County
Solar + storage
20.0 MWWithdrawn / abandoned Mcpherson, SDMISO Jun 2020target 2023
Solar project W2-096, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Jul 2010target 2012
Solar + storage project AF2-326, Edgecombe County
Solar + storage
20.0 MWWithdrawn / abandoned Edgecombe, NCPJM Mar 2020target 2023
Solar + storage project AG1-503, Orange County
Solar + storage · Oak Green Solar LLC
20.0 MWWithdrawn / abandoned Orange, VAPJM Sep 2020target 2023
Solar project AF2-318, Bradford County
Solar
20.0 MWWithdrawn / abandoned Bradford, PAPJM Mar 2020target 2022
Page 372 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)