πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

SOLAR Β· NYISO

East Hampton - Phase 3

East Hampton - Phase 3 is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedMay 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
435
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
East Hampton Solar Farm 2, LLC
Connection point (POI)
Amagansett Substation 69KV
Location
Suffolk County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
21 April 2014
Withdrawn
May 2014

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem