🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2023 requests) — page 35

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,063551.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,063 requests · page 35 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 918047, Chesterfield County
Solar
74.9 MWWithdrawn / abandoned Chesterfield, SCSoutheast Sep 2023
Solar project 919085, Kershaw County
Solar
74.9 MWWithdrawn / abandoned Kershaw, SCSoutheast Sep 2023
Solar project 213, Aiken County
Solar
74.9 MWWithdrawn / abandoned Aiken, SCSoutheast Jun 2023target 2025
Solar project 914241, Anderson County
Solar
74.9 MWWithdrawn / abandoned Anderson, SCSoutheast Sep 2023
Solar project 914237, Greenwood County
Solar
74.9 MWWithdrawn / abandoned Greenwood, SCSoutheast Sep 2023
Solar project 918639, Laurens County
Solar
74.9 MWWithdrawn / abandoned Laurens, SCSoutheast Sep 2023
Solar project 920179, Union County
Solar
74.9 MWWithdrawn / abandoned Union, SCSoutheast Sep 2023
Solar project 911187, Sumter County
Solar
74.9 MWWithdrawn / abandoned Sumter, SCSoutheast Sep 2023
Solar project 915737, Greenwood County
Solar
74.9 MWWithdrawn / abandoned Greenwood, SCSoutheast Sep 2023
Solar project 339, Suwannee County
Solar · Duke Energy Florida, LLC
74.9 MWWithdrawn / abandoned Suwannee, FLSoutheast Nov 2023target 2026
Battery storage project 228, Berkeley County
Battery storage
74.9 MWWithdrawn / abandoned Berkeley, SCSoutheast Jun 2023target 2028
Solar project 912861, Greenwood County
Solar
74.9 MWWithdrawn / abandoned Greenwood, SCSoutheast Sep 2023
Solar project 918039, Cumberland County
Solar
74.9 MWWithdrawn / abandoned Cumberland, NCSoutheast Sep 2023
Solar project 919467, Greenwood County
Solar
74.9 MWWithdrawn / abandoned Greenwood, SCSoutheast Sep 2023
Solar project 332, Hamilton County
Solar · Duke Energy Florida, LLC
74.9 MWWithdrawn / abandoned Hamilton, FLSoutheast Jul 2023target 2025
Solar project 212, Calhoun County
Solar
74.8 MWWithdrawn / abandoned Calhoun, SCSoutheast Jun 2023target 2026
Solar project 107, Pasco County
Solar
74.5 MWWithdrawn / abandoned Pasco, FLSoutheast Sep 2023target 2025
Solar project 589, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2032
Solar project 590, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2032
Solar project 494, Indian River County
Solar · FPL
74.5 MWWithdrawn / abandoned Indian River, FLSoutheast Jan 2023target 2028
Solar project 578, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2029
Solar project 581, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2030
Solar project 575, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2028
Solar project 588, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2032
Solar project 573, Charlotte County
Solar · FPL
74.5 MWWithdrawn / abandoned Charlotte, FLSoutheast Jul 2023target 2029
Solar project 577, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2029
Solar project 582, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2030
Solar project 102, Hillsborough County
Solar
74.5 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2023target 2025
Solar project 583, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2031
Solar project 598, Gadsden County
Solar · Third Party
74.5 MWWithdrawn / abandoned Gadsden, FLSoutheast Sep 2023target 2027
Battery storage project 224, Orangeburg County
Battery storage
74.5 MWWithdrawn / abandoned Orangeburg, SCSoutheast Jun 2023target 2028
Solar project 553, Palm Beach County
Solar · FPL
74.5 MWWithdrawn / abandoned Palm Beach, FLSoutheast Jan 2023target 2028
Solar project 512, Manatee County
Solar · FPL
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Jan 2023target 2029
Solar project 586, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2031
Solar project 585, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2031
Solar project 579, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2029
Solar project 576, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2028
Solar project 105, Hillsborough County
Solar
74.5 MWWithdrawn / abandoned Hillsborough, FLSoutheast Jun 2023target 2025
Solar project 572, Charlotte County
Solar · FPL
74.5 MWWithdrawn / abandoned Charlotte, FLSoutheast Jul 2023target 2028
Solar project 597, Nassau County
Solar · FPL
74.5 MWWithdrawn / abandoned Nassau, FLSoutheast Jul 2023target 2028
Solar project 574, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2028
Solar project 580, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2030
Solar project 495, Palm Beach County
Solar · FPL
74.5 MWWithdrawn / abandoned Palm Beach, FLSoutheast Jan 2023target 2027
Solar project 584, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2031
Solar project 560, Hendry County
Solar · FPL
74.5 MWWithdrawn / abandoned Hendry, FLSoutheast Jul 2023target 2028
Solar project 109, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Oct 2023target 2026
Solar project 587, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2032
Solar project 508, Martin County
Solar · FPL
74.5 MWWithdrawn / abandoned Martin, FLSoutheast Jan 2023target 2030
Solar project 592, Martin County
Solar · FPL
74.5 MWWithdrawn / abandoned Martin, FLSoutheast Jul 2023target 2029
Solar project 591, Martin County
Solar · FPL
74.5 MWWithdrawn / abandoned Martin, FLSoutheast Jul 2023target 2028
Page 35 of 42

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)