United States › Grid › Interconnection queues › Arizona

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Arizona, West — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25985.6 GW
Active in queue85.6 GW259 requests
Agreement signed3,350 MW11 requests
Withdrawn650167.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

259 requests · page 3 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project Q497, Navajo County
Onshore wind
300 MWIn study Navajo, AZWest Mar 2023target 2027
Solar + storage project 2023-G11, Cochise County
Solar + storage
300 MWIn study Cochise, AZWest Aug 2023target 2028
Solar + storage project Q350, Yuma County
Solar + storage
300 MWUnder construction Yuma, AZWest Sep 2020target 2022
Other project 78, Apache County
Other
300 MWIn study Apache, AZWest Feb 2020target 2023
Battery storage project Q280, Maricopa County
Battery storage
300 MWAgreement signed Maricopa, AZWest Sep 2018target 2022
Battery storage project Q467, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Mar 2022target 2026
Solar + storage project 2022-G9, Pinal County
Solar + storage
300 MWIn study Pinal, AZWest Jul 2022target 2025
Onshore wind project NC5-009, Mohave County
Onshore wind
300 MWIn study Mohave, AZWest Apr 2022target 2027
Solar + storage project 124, Pinal County
Solar + storage
300 MWIn study Pinal, AZWest Jun 2022target 2025
Battery storage project Q314, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Sep 2019target 2022
Other project Q597, Yuma County
Other
300 MWIn study Yuma, AZWest May 2025target 2029
Solar + storage project 2023-G17, Mohave County
Solar + storage
300 MWIn study Mohave, AZWest Dec 2023target 2027
Other project Q586, Maricopa County
Other
300 MWIn study Maricopa, AZWest May 2025target 2030
Solar + storage project Q443, Yuma County
Solar + storage
300 MWIn study Yuma, AZWest Mar 2022target 2027
Other project Q570, Yuma County
Other
300 MWIn study Yuma, AZWest May 2024target 2028
Onshore wind project 118, Apache County
Onshore wind
300 MWIn study Apache, AZWest Apr 2022target 2025
Solar + storage project Q2402, Maricopa County
Solar + storage
300 MWIn study Maricopa, AZWest Feb 2024target 2027
Battery storage project Q375, Maricopa County
Battery storage
300 MWAgreement signed Maricopa, AZWest Mar 2021target 2023
Other project Q578, Pinal County
Other
300 MWIn study Pinal, AZWest Apr 2025target 2029
Solar + storage project Q437, Maricopa County
Solar + storage
300 MWIn study Maricopa, AZWest Sep 2021target 2024
Other project Q607, Maricopa County
Other
300 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q582, Maricopa County
Other
275 MWIn study Maricopa, AZWest May 2025target 2030
Solar + storage project 119, Greenlee County
Solar + storage
270 MWIn study Greenlee, AZWest Apr 2022target 2027
Solar + storage project Q392, Pinal County
Solar + storage
270 MWIn study Pinal, AZWest Mar 2021target 2024
Battery storage project Q2510, Maricopa County
Battery storage
264 MWIn study Maricopa, AZWest Feb 2025target 2028
Solar + storage project 2024-G3, Maricopa County
Solar + storage
260 MWIn study Maricopa, AZWest Mar 2024target 2027
Solar + storage project Q475, Maricopa County
Solar + storage
250 MWIn study Maricopa, AZWest Mar 2022target 2025
Other project Q593, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Solar + storage project 2023-G9, La Paz County
Solar + storage
250 MWIn study La Paz, AZWest Jul 2023target 2027
Other project Q595, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q594, Pinal County
Other
250 MWIn study Pinal, AZWest May 2025target 2029
Other project Q618, Pima County
Other
250 MWIn study Pima, AZWest May 2025target 2030
Solar + storage project 2023-G14, Pinal County
Solar + storage
250 MWIn study Pinal, AZWest Oct 2023target 2027
Solar + storage project 2022-G1, La Paz County
Solar + storage
250 MWIn study La Paz, AZWest Jan 2022target 2025
Other project 112, Apache County
Other
250 MWIn study Apache, AZWest Jan 2022target 2025
Other project Q598, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Solar + storage project 2022-G7, Maricopa County
Solar + storage
250 MWIn study Maricopa, AZWest Jun 2022target 2025
Other project Q558, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2024target 2028
Solar + storage project 2023-G8, La Paz County
Solar + storage
250 MWIn study La Paz, AZWest Jul 2023target 2027
Solar + storage project Q446, Maricopa County
Solar + storage
250 MWIn study Maricopa, AZWest Mar 2022target 2025
Other project 100, Pima County
Other
250 MWIn study Pima, AZWest Oct 2021target 2024
Solar + storage project Q377, Maricopa County
Solar + storage
250 MWPaused / redesign Maricopa, AZWest Mar 2021target 2024
Other project 87, Apache County
Other
250 MWIn study Apache, AZWest Dec 2020target 2023
Solar + storage project Q569, Pinal County
Solar + storage
250 MWIn study Pinal, AZWest May 2024target 2028
Solar + storage project Q252, Yuma County
Solar + storage
250 MWUnder construction Yuma, AZWest Mar 2017target 2021
Battery storage project Q427, Maricopa County
Battery storage
250 MWIn study Maricopa, AZWest Sep 2021target 2025
Solar + storage project Q354, Maricopa County
Solar + storage
250 MWIn study Maricopa, AZWest Sep 2020target 2023
Battery storage project Q278, Maricopa County
Battery storage
250 MWIn study Maricopa, AZWest Jun 2018target 2021
Solar + storage project Q378, Maricopa County
Solar + storage
250 MWPaused / redesign Maricopa, AZWest Mar 2021target 2024
Other project 86, Apache County
Other
250 MWIn study Apache, AZWest Dec 2020target 2023

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20142025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)